1004.649 Northwest Regional Data Center.
(1) For the purpose of serving its state agency customers, the Northwest Regional Data Center at Florida State University is designated as a primary data center and shall:
(a) Operate under a governance structure that represents its customers proportionally.
(b) Maintain an appropriate cost-allocation methodology that accurately bills state agency customers based solely on the actual direct and indirect costs of the services provided to state agency customers, and prohibits the subsidization of nonstate agency customers’ costs by state agency customers.
(c) Enter into a service-level agreement with each state agency customer to provide services as defined and approved by the governing board of the center. At a minimum, such service-level agreements must:
1. Identify the parties and their roles, duties, and responsibilities under the agreement;
2. State the duration of the agreement term and specify the conditions for renewal;
3. Identify the scope of work;
4. Establish the services to be provided, the business standards that must be met for each service, the cost of each service, and the process by which the business standards for each service are to be objectively measured and reported;
5. Provide a timely billing methodology for recovering the cost of services provided; and
6. Provide a procedure for modifying the service-level agreement to address any changes in projected costs of service.
(d) Provide to the Board of Governors the total annual budget by major expenditure category, including, but not limited to, salaries, expenses, operating capital outlay, contracted services, or other personnel services by July 30 each fiscal year.
(e) Provide to each state agency customer its projected annual cost for providing the agreed-upon data center services by September 1 each fiscal year.
(f) Provide a plan for consideration by the Legislative Budget Commission if the governing body of the center approves the use of a billing rate schedule after the start of the fiscal year that increases any state agency customer’s costs for that fiscal year.
(2) The Northwest Regional Data Center’s designation as a primary data center for purposes of serving its state agency customers may be terminated if:
(a) The center requests such termination to the Board of Governors, the Senate President, and the Speaker of the House of Representatives; or
(b) The center fails to comply with the provisions of this section.
(3) If such designation is terminated, the center shall have 1 year to provide for the transition of its state agency customers to the Southwood Shared Resource Center or the Northwood Shared Resource Center.
History.s. 6, ch. 2011-63; s. 3, ch. 2012-142.