Representative Reagan offered the following: |
|
13
|
|
|
14
|
Amendment (with title amendment) |
|
15
|
Remove everything after the enacting clause, and insert: |
|
16
|
Section 1. Section 218.70, Florida Statutes, is amended to |
|
17
|
read: |
|
18
|
218.70 Popular nameShort title.--This part may be cited |
|
19
|
as the "Local GovernmentFloridaPrompt Payment Act." |
|
20
|
Section 2. Subsections (2), (6), and (7) of section |
|
21
|
218.72, Florida Statutes, are amended to read: |
|
22
|
218.72 Definitions.--As used in this part: |
|
23
|
(2) "Local governmental entity" means a county or |
|
24
|
municipal government, school board, school district, authority, |
|
25
|
special taxing district, other political subdivision, community |
|
26
|
college,or any office, board, bureau, commission, department, |
|
27
|
branch, division, or institution thereof or any project |
|
28
|
supported by county or municipal funds. |
|
29
|
(6) "Vendor" means any person who sells goods or services, |
|
30
|
sells or leases personal property, or leases real property |
|
31
|
directlyto a local government entity. |
|
32
|
(7) "Construction services" means all labor, services, and |
|
33
|
materials provided in connection with the construction, |
|
34
|
alteration, repair, demolition, reconstruction, or any other |
|
35
|
improvements to real property that require a license under parts |
|
36
|
I and II of chapter 489. |
|
37
|
Section 3. Subsection (6) of section 218.735, Florida |
|
38
|
Statutes, is amended, present subsection (7) of that section is |
|
39
|
redesignated as subsection (9), and new subsections (7) and (8) |
|
40
|
are added to that section, to read: |
|
41
|
218.735 Timely payment for purchases of construction |
|
42
|
services.-- |
|
43
|
(6) When a contractor receives payment from a local |
|
44
|
governmental entity for labor, services, or materials furnished |
|
45
|
by subcontractors and suppliers hired by the contractor, the |
|
46
|
contractor shall remit payment due to those subcontractors and |
|
47
|
suppliers within 1015days after the contractor's receipt of |
|
48
|
payment. When a subcontractor receives payment from a contractor |
|
49
|
for labor, services, or materials furnished by subcontractors |
|
50
|
and suppliers hired by the subcontractor, the subcontractor |
|
51
|
shall remit payment due to those subcontractors and suppliers |
|
52
|
within 1015days after the subcontractor's receipt of payment. |
|
53
|
Nothing herein shall prohibit a contractor or subcontractor from |
|
54
|
disputing, pursuant to the terms of the relevant contract, all |
|
55
|
or any portion of a payment alleged to be due to another party. |
|
56
|
In the event of such a dispute, the contractor or subcontractor |
|
57
|
may withhold the disputed portion of any such payment if the |
|
58
|
contractor or subcontractor notifies the party whose payment is |
|
59
|
disputed, in writing, of the amount in dispute and the actions |
|
60
|
required to cure the dispute. The contractor or subcontractor |
|
61
|
must pay all undisputed amounts due within the time limits |
|
62
|
imposed by this section. |
|
63
|
(7)(a) Each contract for construction services between a |
|
64
|
local government entity and vendor must provide for the |
|
65
|
development of a list of items required to render complete, |
|
66
|
satisfactory, and acceptable the construction services purchased |
|
67
|
by the local government. The contract must specify the process |
|
68
|
for the development of the list, including responsibilities of |
|
69
|
the local government and vendor in developing and reviewing the |
|
70
|
list and a reasonable time for developing such list as follows: |
|
71
|
1. For construction projects with an estimated cost less |
|
72
|
than $10 million, within 30 days after reaching substantial |
|
73
|
completion of the construction services purchased as defined in |
|
74
|
the contract, or, if not defined in the contract, upon reaching |
|
75
|
beneficial occupancy or use; or |
|
76
|
2. For construction projects with an estimated cost of $10 |
|
77
|
million or more, within 30 days, unless otherwise extended by |
|
78
|
contract not to exceed 90 days, after reaching substantial |
|
79
|
completion of the construction services purchased as defined in |
|
80
|
the contract, or, if not defined in the contract, upon reaching |
|
81
|
beneficial occupancy or use. |
|
82
|
(b) If the contract between the local government entity |
|
83
|
and vendor relates to the purchase of construction services on |
|
84
|
more than one building or structure, or involves a multiphased |
|
85
|
project, the contract shall provide for the development of a |
|
86
|
list of items required to render complete, satisfactory, and |
|
87
|
acceptable the construction services purchased for each |
|
88
|
building, structure, or phase of the project in accordance with |
|
89
|
the timeframes specified in subparagraph (a)1. or subparagraph |
|
90
|
(a)2. |
|
91
|
(c) The failure to include any corrective work or pending |
|
92
|
items not yet completed on the list developed pursuant to this |
|
93
|
subsection shall not alter the responsibility of the vendor to |
|
94
|
complete all the purchased construction services as defined in |
|
95
|
the contract. |
|
96
|
(d) Upon completion of all items on the list, or such |
|
97
|
other time defined in the contract, the vendor may submit a |
|
98
|
payment request for the appropriate amount of retainage. The |
|
99
|
local government may withhold an amount not to exceed 150 |
|
100
|
percent of the total costs to complete any incomplete items on |
|
101
|
the list. |
|
102
|
(e) All items that require correction under the contract |
|
103
|
and that are identified after the preparation and delivery of |
|
104
|
the list shall remain the obligation of the vendor as defined by |
|
105
|
the contract. |
|
106
|
(f) Warranty items may not affect the final payment of |
|
107
|
retainage as provided in this section or as may be provided in |
|
108
|
the contract between the vendor and its subcontractors and |
|
109
|
suppliers. |
|
110
|
(g) If a local government entity fails to comply with its |
|
111
|
responsibilities to develop the list required under paragraph |
|
112
|
(a) or paragraph(b), as defined in the contract, and the |
|
113
|
timeframes provided in subparagraph(a)1. or subparagraph (a)2., |
|
114
|
the vendor may submit a payment request for the appropriate |
|
115
|
amount of retainage. The local government entity shall not be |
|
116
|
required to pay or process any request for payment of retainage |
|
117
|
if the vendor has, in whole or in part, failed to cooperate with |
|
118
|
the local government in the development of the list; failed to |
|
119
|
perform its contractual responsibilities, if any, with regard to |
|
120
|
the development of the list; or if paragraph (8)(d) applies. |
|
121
|
(8)(a) In any public construction project, a local |
|
122
|
government entity may withhold an amount not exceeding 10 |
|
123
|
percent of each progress payment made to the vendor until the |
|
124
|
local government project has reached 50-percent completion. |
|
125
|
After reaching 50-percent completion, the local government must |
|
126
|
reduce to 5 percent the amount of retainage withheld from each |
|
127
|
subsequent progress payment made to the vendor. However, |
|
128
|
notwithstanding the provisions of this subsection, a |
|
129
|
municipality with a population of 25,000 or fewer, or a county |
|
130
|
with a population of 100,000 or fewer, may withhold retainage in |
|
131
|
an amount not exceeding 10 percent of each progress payment made |
|
132
|
to the vendor until final completion and acceptance of the |
|
133
|
project by the local government. For purposes of this |
|
134
|
subsection, the term "50-percent completion" means as defined in |
|
135
|
the contract between the local government entity and the vendor, |
|
136
|
or, if not defined in the contract, the point at which the local |
|
137
|
government has expended 50 percent of the total project costs |
|
138
|
identified in the contract, plus all change orders and other |
|
139
|
additions issued subsequent to the approval of the contract by |
|
140
|
the governing body of the local government, and the level of |
|
141
|
actual project construction is equivalent to such expenditure of |
|
142
|
funds. |
|
143
|
(b) After 50-percent completion, the vendor may present to |
|
144
|
the local government entity a payment request for up to one-half |
|
145
|
of the retainage amount held by the local government. The local |
|
146
|
government entity shall promptly make payment to the vendor, |
|
147
|
unless the local government has grounds, pursuant to the |
|
148
|
contract or as provided in paragraph (d), for withholding the |
|
149
|
payment of retainage. If the local government makes payment of |
|
150
|
retainage to the vendor under this paragraph, the vendor shall |
|
151
|
timely remit payment of such retainage to the appropriate |
|
152
|
subcontractors and suppliers. |
|
153
|
(c) After 50-percent completion, the vendor may elect to |
|
154
|
withhold retainage from payments to its subcontractors at a rate |
|
155
|
higher than 5 percent. The specific amount to be withheld must |
|
156
|
be determined on a case-by-case basis and must be based on the |
|
157
|
vendor's assessment of the subcontractor's past performance, the |
|
158
|
likelihood that such performance will continue, and the vendor's |
|
159
|
ability to rely on other safeguards. The vendor shall notify the |
|
160
|
subcontractor, in writing, of its determination to withhold more |
|
161
|
than 5 percent of the progress payment and the reasons for |
|
162
|
making that determination, and the vendor may not request the |
|
163
|
release of such retained funds from the local government. |
|
164
|
(d) Nothing in this section requires the local government |
|
165
|
to pay or release any amounts that are the subject of a good- |
|
166
|
faith dispute, the subject of an action brought pursuant to s. |
|
167
|
255.05, or otherwise the subject of a claim or demand by the |
|
168
|
local government or vendor. |
|
169
|
(e) The timeframes set forth in this section for payment |
|
170
|
of payment requests apply to any payment request for retainage |
|
171
|
made pursuant to this subsection. |
|
172
|
Section 4. Section 255.0705, Florida Statutes, is created |
|
173
|
to read: |
|
174
|
255.0705 Short title.--Sections 255.0705-255.078 may be |
|
175
|
cited as the "Florida Prompt Payment Act." |
|
176
|
Section 5. Subsections (2) and (3) of section 255.071, |
|
177
|
Florida Statutes, are amended to read: |
|
178
|
255.071 Payment of subcontractors, sub-subcontractors, |
|
179
|
materialmen, and suppliers on construction contracts for public |
|
180
|
projects.-- |
|
181
|
(2) The failure to pay any undisputed obligations for such |
|
182
|
labor, services, or materials within 30 days after the date the |
|
183
|
labor, services, or materials were furnished and payment for |
|
184
|
such labor, services, or materials became due, or within 1030 |
|
185
|
days after the date payment for such labor, services, or |
|
186
|
materials is received, whichever last occurs, shall entitle any |
|
187
|
person providing such labor, services, or materials to the |
|
188
|
procedures specified in subsection (3) and the remedies provided |
|
189
|
in subsection(4). |
|
190
|
(3) Any person providing labor, services, or materials for |
|
191
|
the construction of a public building, for the prosecution and |
|
192
|
completion of a public work, or for repairs upon a public |
|
193
|
building or public work improvements to real property may file a |
|
194
|
verified complaint alleging: |
|
195
|
(a) The existence of a contract for providing such labor, |
|
196
|
services, or materials to improve real property. |
|
197
|
(b) A description of the labor, services, or materials |
|
198
|
provided and alleging that the labor, services, or materials |
|
199
|
were provided in accordance with the contract. |
|
200
|
(c) The amount of the contract price. |
|
201
|
(d) The amount, if any, paid pursuant to the contract. |
|
202
|
(e) The amount that remains unpaid pursuant to the |
|
203
|
contract and the amount thereof that is undisputed. |
|
204
|
(f) That the undisputed amount has remained due and |
|
205
|
payable pursuant to the contract for more than 30 days after the |
|
206
|
date the labor or services were accepted or the materials were |
|
207
|
received. |
|
208
|
(g) That the person against whom the complaint was filed |
|
209
|
has received payment on account of the labor, services, or |
|
210
|
materials described in the complaint more than 1030days prior |
|
211
|
to the date the complaint was filed. |
|
212
|
Section 6. Section 255.072, Florida Statutes, is created |
|
213
|
to read: |
|
214
|
255.072 Definitions.--As used in ss. 255.073-255.078, the |
|
215
|
term: |
|
216
|
(1) "Agent" means project architect, project engineer, or |
|
217
|
any other agency or person acting on behalf of a public entity. |
|
218
|
(2) "Construction services" means all labor, services, and |
|
219
|
materials provided in connection with the construction, |
|
220
|
alteration, repair, demolition, reconstruction, or any other |
|
221
|
improvements to real property. The term "construction services" |
|
222
|
does not include contracts or work performed for the Department |
|
223
|
of Transportation. |
|
224
|
(3) "Payment request" means an invoice or request for |
|
225
|
payment for construction services which conforms with all |
|
226
|
statutory requirements and with all requirements specified by |
|
227
|
the public entity to which the payment request is submitted. |
|
228
|
(4) "Public entity" means the state, a state university, |
|
229
|
or any office, board, bureau, commission, department, branch, |
|
230
|
division, or institution thereof, or any project supported by |
|
231
|
state funds, but does not include a local government entity as |
|
232
|
defined in s. 218.72. |
|
233
|
(5) "Purchase" means the purchase of construction |
|
234
|
services. |
|
235
|
(6) "Vendor" means any person providing construction |
|
236
|
services directly to a public entity. |
|
237
|
Section 7. Section 255.073, Florida Statutes, is created |
|
238
|
to read: |
|
239
|
255.073 Timely payment for purchases of construction |
|
240
|
services.-- |
|
241
|
(1) Except as otherwise provided in ss. 255.072-255.078, |
|
242
|
s. 215.422 governs the timely payment for construction services |
|
243
|
by a public entity under this act. |
|
244
|
(2) If a public entity disputes a portion of a payment |
|
245
|
request, the undisputed portion must be timely paid, in |
|
246
|
accordance with subsection(1). |
|
247
|
(3) When a vendor receives payment from a public entity |
|
248
|
for labor, services, or materials furnished by subcontractors |
|
249
|
and suppliers hired by the vendor, the vendor shall remit |
|
250
|
payment due to those subcontractors and suppliers within 10 days |
|
251
|
after the vendor's receipt of payment. When a subcontractor |
|
252
|
receives payment from a vendor for labor, services, or materials |
|
253
|
furnished by subcontractors and suppliers hired by the |
|
254
|
subcontractor, the subcontractor shall remit payment due to |
|
255
|
those subcontractors and suppliers within 10 days after the |
|
256
|
subcontractor's receipt of payment. This subsection does not |
|
257
|
prohibit a vendor or subcontractor from disputing, pursuant to |
|
258
|
the terms of the relevant contract, all or any portion of a |
|
259
|
payment alleged to be due to another party. If such a dispute |
|
260
|
occurs, the vendor or subcontractor may withhold the disputed |
|
261
|
portion of any such payment if the vendor or subcontractor |
|
262
|
notifies the party whose payment is disputed, in writing, of the |
|
263
|
amount in dispute and the actions required to cure the dispute. |
|
264
|
The vendor or subcontractor must pay all undisputed amounts due |
|
265
|
within the time limits imposed by this section. |
|
266
|
(4) All payments due under this section and not made |
|
267
|
within the time periods specified by this section shall bear |
|
268
|
interest at the rate of 1 percent per month, or the rate |
|
269
|
specified by contract, whichever is greater. |
|
270
|
Section 8. Section 255.074, Florida Statutes, is created |
|
271
|
to read: |
|
272
|
255.074 Procedures for calculation of payment due dates.-- |
|
273
|
(1) Each public entity shall establish procedures whereby |
|
274
|
each payment request received by the public entity is marked as |
|
275
|
received on the date on which it is delivered to an agent or |
|
276
|
employee of the public entity or of a facility or office of the |
|
277
|
public entity. |
|
278
|
(2) If the terms under which a purchase is made allow for |
|
279
|
partial deliveries and a payment request is submitted for a |
|
280
|
partial delivery, the time for payment for the partial delivery |
|
281
|
must be calculated from the time of the partial delivery and the |
|
282
|
submission of the payment request in the same manner as provided |
|
283
|
in s. 255.073. |
|
284
|
(3) The public entity must submit a payment request to the |
|
285
|
Chief Financial Officer for payment no more than 25 days after |
|
286
|
receipt of the payment request. |
|
287
|
Section 9. Section 255.075, Florida Statutes, is created |
|
288
|
to read: |
|
289
|
255.075 Mandatory interest.--A contract between a public |
|
290
|
entity and a vendor or a provider of construction services may |
|
291
|
not prohibit the collection of late payment interest charges |
|
292
|
allowable under ss. 255.072-255.078. |
|
293
|
Section 10. Section 255.076, Florida Statutes, is created |
|
294
|
to read: |
|
295
|
255.076 Improper payment request; resolution of |
|
296
|
disputes.-- |
|
297
|
(1) If a vendor submits an improper payment request, the |
|
298
|
public entity shall, within 10 days after receiving the improper |
|
299
|
payment request, notify the vendor that the payment request is |
|
300
|
improper and indicate what corrective action on the part of the |
|
301
|
vendor is needed to make the payment request proper. |
|
302
|
(2) If a dispute occurs between a vendor and a public |
|
303
|
entity concerning payment of a payment request, the dispute must |
|
304
|
be resolved as provided in this section. Each public entity |
|
305
|
shall establish a dispute resolution procedure to be followed by |
|
306
|
the public entity if such a dispute occurs. The procedure must |
|
307
|
provide that proceedings to resolve the dispute must commence |
|
308
|
not later than 45 days after the date on which the public entity |
|
309
|
received the payment request and must conclude by final decision |
|
310
|
of the public entity not later than 60 days after the date on |
|
311
|
which the public entity received the payment request. Such |
|
312
|
procedures are not subject to chapter 120 and do not constitute |
|
313
|
an administrative proceeding that prohibits a court from |
|
314
|
deciding de novo any action arising out of the dispute. If the |
|
315
|
dispute is resolved in favor of the public entity, interest |
|
316
|
charges begin to accrue 15 days after the public entity's final |
|
317
|
decision. If the dispute is resolved in favor of the vendor, |
|
318
|
interest begins to accrue as of the original date the payment |
|
319
|
became due. |
|
320
|
(3) In an action to recover amounts due under ss. 255.072- |
|
321
|
255.078, the court shall award court costs and reasonable |
|
322
|
attorney's fees, including fees incurred through any appeal, to |
|
323
|
the prevailing party, if the court finds that the nonprevailing |
|
324
|
party withheld any portion of the payment that is the subject of |
|
325
|
the action without any reasonable basis in law or fact to |
|
326
|
dispute the prevailing party's claim to those amounts. |
|
327
|
Section 11. Section 255.077, Florida Statutes, is created |
|
328
|
to read: |
|
329
|
255.077 Project closeout and payment of retainage.-- |
|
330
|
(1) A public entity must present to the vendor a final |
|
331
|
punch list of all items required to render complete, |
|
332
|
satisfactory, and acceptable the construction services |
|
333
|
purchased, within 30 days after the earliest of the following: |
|
334
|
(a) Issuance of a temporary or final certificate of |
|
335
|
occupancy, if applicable; |
|
336
|
(b) Substantial completion of the construction services |
|
337
|
purchased, as defined in the contract; or |
|
338
|
(c) Beneficial occupancy or use of the structure, |
|
339
|
building, facility, or improvement that is the subject of the |
|
340
|
construction services purchased, as defined in the contract. |
|
341
|
(2) If the purchase relates to construction services on |
|
342
|
more than one building or structure, the public entity shall |
|
343
|
prepare a final punch list for each building or structure. The |
|
344
|
public entity must present to the vendor a final punch list with |
|
345
|
regard to each building or structure within 30 days after the |
|
346
|
earliest of the following: |
|
347
|
(a) Issuance of a temporary or final certificate of |
|
348
|
occupancy on the particular building or structure, if |
|
349
|
applicable; |
|
350
|
(b) Substantial completion of the particular building or |
|
351
|
structure, as defined in the contract; or |
|
352
|
(c) Beneficial occupancy or use of the particular |
|
353
|
structure, building, facility, or improvement, as defined in the |
|
354
|
contract. |
|
355
|
|
|
356
|
Unless the contract provides otherwise, the public entity shall |
|
357
|
pay out retainage to the vendor based upon the value of the |
|
358
|
construction services rendered with regard to that structure, |
|
359
|
building, facility, or improvement as compared to the total |
|
360
|
value of the purchase. |
|
361
|
(3) Upon completion of all items on the final punch list |
|
362
|
or within 30 days after issuance of the punch list, whichever |
|
363
|
occurs sooner, the vendor shall submit a payment request for the |
|
364
|
appropriate amount of retainage. The owner may withhold up to |
|
365
|
150 percent of the cost to complete any incomplete final |
|
366
|
punchlist items. Thereafter, ss. 255.072-255.076 apply to the |
|
367
|
payment of any payment request for retainage. |
|
368
|
(4) If the public entity fails to present to the vendor a |
|
369
|
final punch list within the time periods provided in subsection |
|
370
|
(1) or subsection (2), the project is considered to be complete |
|
371
|
and the vendor shall submit a payment request for the |
|
372
|
appropriate amount of retainage. Thereafter, ss. 255.072-255.076 |
|
373
|
apply to the payment of any payment request for retainage. |
|
374
|
(5) All items that require correction under the contract |
|
375
|
which are identified subsequent to preparation and delivery of |
|
376
|
the final punch list must be considered warranty items or make- |
|
377
|
good items, and such items have no effect on the final payment |
|
378
|
of retainage provided in this section. |
|
379
|
Section 12. Section 255.078, Florida Statutes, is created |
|
380
|
to read: |
|
381
|
255.078 Public construction retainage.-- |
|
382
|
(1) From the commencement of a public construction project |
|
383
|
that is subject to ss. 255.072-255.078 until 50-percent of the |
|
384
|
contract value has been earned, a public entity may not withhold |
|
385
|
as retainage more than 10 percent of each progress payment to |
|
386
|
the vendor. When 50-percent of the contract value has been |
|
387
|
earned, the vendor may submit a payment request to the public |
|
388
|
entity for up to one-half of the retainage withheld up to that |
|
389
|
time. |
|
390
|
(2) After 50-percent of the contract value has been |
|
391
|
earned, the public entity may not withhold as retainage more |
|
392
|
than 5 percent of each progress payment to the vendor. However, |
|
393
|
the vendor may withhold retainage from payments to its |
|
394
|
subcontractors at a rate higher than 5 percent. The specific |
|
395
|
amount to be withheld must be determined on a case-by-case basis |
|
396
|
and must be based on the vendor's assessment of the |
|
397
|
subcontractor's past performance, the likelihood that such |
|
398
|
performance will continue, and the vendor's ability to rely on |
|
399
|
other safeguards. The vendor shall notify the subcontractor, in |
|
400
|
writing, of its determination to withhold more than 5 percent of |
|
401
|
the progress payment and the reasons for making that |
|
402
|
determination. |
|
403
|
(3) This section does not require the payment or release |
|
404
|
of amounts that are the subject of a good-faith dispute. |
|
405
|
(4) Sections 255.072-255.076 apply to the payment of any |
|
406
|
payment request for retainage. |
|
407
|
Section 13. Paragraph (a) of subsection (2) is amended and |
|
408
|
subsections (10) and (11) are added to section 255.05, Florida |
|
409
|
Statutes, to read: |
|
410
|
255.05 Bond of contractor constructing public buildings; |
|
411
|
form; action by materialmen.-- |
|
412
|
(2)(a)1. If a claimant is no longer furnishing labor, |
|
413
|
services, or materials on a project, a contractor or the |
|
414
|
contractor's agent or attorney may elect to shorten the |
|
415
|
prescribed time in this paragraph within which an action to |
|
416
|
enforce any claim against a payment bond provided pursuant to |
|
417
|
this section may be commenced by recording in the clerk's office |
|
418
|
a notice in substantially the following form: |
|
419
|
|
|
420
|
NOTICE OF CONTEST OF CLAIM AGAINST PAYMENT BOND |
|
421
|
|
|
422
|
To: . . . (Name and address of claimant) . . . |
|
423
|
|
|
424
|
You are notified that the undersigned contests your notice |
|
425
|
of nonpayment, dated ____________, ________, and served on the |
|
426
|
undersigned on ____________, ________, and that the time within |
|
427
|
which you may file suit to enforce your claim is limited to 60 |
|
428
|
days after the date of service of this notice. |
|
429
|
|
|
430
|
DATED on ____________, ________. |
|
431
|
|
|
432
|
Signed: . . . (Contractor or Attorney) . . . |
|
433
|
|
|
434
|
The claim of any claimant upon whom such notice is served and |
|
435
|
who fails to institute a suit to enforce his or her claim |
|
436
|
against the payment bond within 60 days after service of such |
|
437
|
notice shall be extinguished automatically. The clerk shall mail |
|
438
|
a copy of the notice of contest to the claimant at the address |
|
439
|
shown in the notice of nonpayment or most recent amendment |
|
440
|
thereto and shall certify to such service on the face of such |
|
441
|
notice and record the notice. Service is complete upon mailing. |
|
442
|
2. A claimant, except a laborer, who is not in privity |
|
443
|
with the contractor shall, before commencing or not later than |
|
444
|
45 days after commencing to furnish labor, materials, or |
|
445
|
supplies for the prosecution of the work, furnish the contractor |
|
446
|
with a notice that he or she intends to look to the bond for |
|
447
|
protection. A claimant who is not in privity with the contractor |
|
448
|
and who has not received payment for his or her labor, |
|
449
|
materials, or supplies shall deliver to the contractor and to |
|
450
|
the surety written notice of the performance of the labor or |
|
451
|
delivery of the materials or supplies and of the nonpayment. The |
|
452
|
notice of nonpayment may be served at any time during the |
|
453
|
progress of the work or thereafter but not before 45 days after |
|
454
|
the first furnishing of labor, services, or materials, and not |
|
455
|
later than 90 days after the final furnishing of the labor, |
|
456
|
services, or materials by the claimant or, with respect to |
|
457
|
rental equipment, not later than 90 days after the date that the |
|
458
|
rental equipment was last on the job site available for use. Any |
|
459
|
notice of nonpayment served by a claimant who is not in privity |
|
460
|
with the contractor which includes sums for retainage must |
|
461
|
specify the portion of the amount claimed for retainage.No |
|
462
|
action for the labor, materials, or supplies may be instituted |
|
463
|
against the contractor or the surety unless both notices have |
|
464
|
been given. Notices required or permitted under this section may |
|
465
|
be served in accordance with s. 713.18. An action, except for an |
|
466
|
action exclusively for recovery of retainage, must be instituted |
|
467
|
against the contractor or the surety on the payment bond or the |
|
468
|
payment provisions of a combined payment and performance bond |
|
469
|
within 1 year after the performance of the labor or completion |
|
470
|
of delivery of the materials or supplies. An action exclusively |
|
471
|
for recovery of retainage must be instituted against the |
|
472
|
contractor or the surety within 1 year after the performance of |
|
473
|
the labor or completion of delivery of the materials or |
|
474
|
supplies, or within 90 days after receipt of final payment (or |
|
475
|
the payment estimate containing the owner's final reconciliation |
|
476
|
of quantities if no further payment is earned and due as a |
|
477
|
result of deductive adjustments) by the contractor or surety, |
|
478
|
whichever comes last. A claimant may not waive in advance his or |
|
479
|
her right to bring an action under the bond against the surety. |
|
480
|
In any action brought to enforce a claim against a payment bond |
|
481
|
under this section, the prevailing party is entitled to recover |
|
482
|
a reasonable fee for the services of his or her attorney for |
|
483
|
trial and appeal or for arbitration, in an amount to be |
|
484
|
determined by the court, which fee must be taxed as part of the |
|
485
|
prevailing party's costs, as allowed in equitable actions. The |
|
486
|
time periods for service of a notice of nonpayment or for |
|
487
|
bringing an action against a contractor or a surety shall be |
|
488
|
measured from the last day of furnishing labor, services, or |
|
489
|
materials by the claimant and shall not be measured by other |
|
490
|
standards, such as the issuance of a certificate of occupancy or |
|
491
|
the issuance of a certificate of substantial completion. |
|
492
|
(10) Notwithstanding any other provision of law to the |
|
493
|
contrary, a claimant may not institute an action for the sole |
|
494
|
purpose of recovery of retainage against the contractor or |
|
495
|
against the surety issuing a payment or performance bond |
|
496
|
pursuant to this section until: |
|
497
|
(a) The public entity has paid out that retainage to the |
|
498
|
contractor and the time provided under ss. 218.70-218.76 or ss. |
|
499
|
255.072-255.078 for payment of that retainage to the claimant |
|
500
|
has expired; |
|
501
|
(b) The claimant has completed all work required under its |
|
502
|
contract and 90 days have passed since the owner's receipt of |
|
503
|
the contractor's last payment request; or |
|
504
|
(c) The claimant has made the written request to the owner |
|
505
|
provided in subsection (11) and has not timely received the |
|
506
|
requested information from the owner. |
|
507
|
(11) An owner shall furnish in writing to a claimant who |
|
508
|
has provided labor, services, or materials to a project, within |
|
509
|
5 business days after receipt of a written request from that |
|
510
|
claimant, the following information: |
|
511
|
(a) The dates of all payment requests received by the |
|
512
|
owner from the contractor. |
|
513
|
(b) The dates of all payments made by the owner to the |
|
514
|
contractor. |
|
515
|
(c) Whether the owner has received the contractor's final |
|
516
|
payment request and, if so, the date the final payment request |
|
517
|
was submitted by the contractor to the owner. |
|
518
|
Section 14. This act shall take effect July 1, 2003. |
|
519
|
|
|
520
|
================= T I T L E A M E N D M E N T ================= |
|
521
|
Remove the entire title, and insert: |
|
522
|
A bill to be entitled |
|
523
|
An act relating to prompt payment for construction |
|
524
|
services; amending s. 218.70, F.S.; providing a short |
|
525
|
title; amending s. 218.72, F.S.; redefining terms used in |
|
526
|
part VII of ch. 218, F.S.; amending s. 218.735, F.S.; |
|
527
|
revising provisions relating to timely payment for |
|
528
|
purchases of construction services; revising deadlines for |
|
529
|
payment; providing procedures for project closeout and |
|
530
|
payment of retainage; providing requirements for local |
|
531
|
government construction retainage; providing that ss. |
|
532
|
218.72-218.76, F.S., apply to the payment of any payment |
|
533
|
request for retainage; creating s. 255.0705, F.S.; |
|
534
|
providing a short title; amending s. 255.071, F.S.; |
|
535
|
revising deadlines for the payment of subcontractors, sub- |
|
536
|
subcontractors, materialmen, and suppliers on construction |
|
537
|
contracts for public projects; creating ss. 255.072, |
|
538
|
255.073, 255.074, 255.075, 255.076, 255.077, 255.078, |
|
539
|
F.S.; providing definitions; providing for timely payment |
|
540
|
for purchases of construction services by a public entity; |
|
541
|
providing procedures for calculating payment due dates; |
|
542
|
providing procedures for handling improper payment |
|
543
|
requests; providing for the resolution of disputes; |
|
544
|
providing for project closeout and payment of retainage; |
|
545
|
providing for public-construction retainage; providing |
|
546
|
that ss. 255.072-255.076, F.S., apply to the payment of |
|
547
|
any payment request for retainage; amending s. 255.05, |
|
548
|
F.S.; providing requirements for certain notices of |
|
549
|
nonpayment served by a claimant who is not in privity with |
|
550
|
the contractor; providing limitations on a claimant's |
|
551
|
institution of certain actions against a contractor or |
|
552
|
surety; providing for certain notices to the claimant; |
|
553
|
providing an effective date. |