9          Remove the entire bill and insert:
10 A bill to be entitled
11          An act relating to prompt payment for construction
12    services; amending s. 218.70, F.S.; providing a popular
13    name; amending s. 218.72, F.S.; redefining terms used in
14    pt. VII of ch. 218, F.S.; amending s. 218.735, F.S.;
15    revising provisions relating to timely payment for
16    purchases of construction services; revising deadlines for
17    payment; providing procedures for project closeout and
18    payment of retainage; providing requirements for local
19    government construction retainage; providing that ss.
20    218.72-218.76, F.S., apply to the payment of any payment
21    request for retainage; creating s. 255.0705, F.S.;
22    providing a popular name; amending s. 255.071, F.S.;
23    revising deadlines for the payment of subcontractors, sub-
24    subcontractors, materialmen, and suppliers on construction
25    contracts for public projects; creating ss. 255.072,
26    255.073, 255.074, 255.075, 255.076, 255.077, and 255.078,
27    F.S.; providing definitions; providing for timely payment
28    for purchases of construction services by a public entity;
29    providing procedures for calculating payment due dates;
30    permitting collection of interest; providing procedures
31    for handling improper payment requests; providing for the
32    resolution of disputes; providing for project closeout and
33    payment of retainage; providing for public construction
34    retainage; providing that ss. 255.072-255.076, F.S., apply
35    to the payment of any payment request for retainage;
36    amending s. 255.05, F.S.; providing requirements for
37    certain notices of nonpayment served by a claimant who is
38    not in privity with the contractor; providing limitations
39    on a claimant's institution of certain actions against a
40    contractor or surety; providing for the tolling of a
41    statute of limitations for bringing suit against a
42    contractor or surety; providing for liability; providing
43    an effective date.
44         
45          Be It Enacted by the Legislature of the State of Florida:
46         
47          Section 1. Section 218.70, Florida Statutes, is amended to
48    read:
49          218.70 Popular nameShort title.--This part shall be known
50    by the popular namemay be cited as the "Local Government
51    FloridaPrompt Payment Act."
52          Section 2. Subsections (2), (6), and (7) of section
53    218.72, Florida Statutes, are amended to read:
54          218.72 Definitions.--As used in this part:
55          (2) "Local governmental entity" means a county or
56    municipal government, school board, school district, authority,
57    special taxing district, other political subdivision, community
58    college,or any office, board, bureau, commission, department,
59    branch, division, or institution thereof or any project
60    supported by county or municipal funds.
61          (6) "Vendor" means any person who sells goods or services,
62    sells or leases personal property, or leases real property
63    directlyto a local governmental entity.
64          (7) "Construction services" means all labor, services, and
65    materials provided in connection with the construction,
66    alteration, repair, demolition, reconstruction, or any other
67    improvements to real property that require a license under parts
68    I and II of chapter 489.
69          Section 3. Subsection (6) of section 218.735, Florida
70    Statutes, is amended, present subsection (7) is renumbered as
71    subsection (9), and new subsections (7) and (8) are added to
72    said section, to read:
73          218.735 Timely payment for purchases of construction
74    services.--
75          (6) When a contractor receives payment from a local
76    governmental entity for labor, services, or materials furnished
77    by subcontractors and suppliers hired by the contractor, the
78    contractor shall remit payment due to those subcontractors and
79    suppliers within 1015days after the contractor's receipt of
80    payment. When a subcontractor receives payment from a contractor
81    for labor, services, or materials furnished by subcontractors
82    and suppliers hired by the subcontractor, the subcontractor
83    shall remit payment due to those subcontractors and suppliers
84    within 1015days after the subcontractor's receipt of payment.
85    Nothing herein shall prohibit a contractor or subcontractor from
86    disputing, pursuant to the terms of the relevant contract, all
87    or any portion of a payment alleged to be due to another party.
88    In the event of such a dispute, the contractor or subcontractor
89    may withhold the disputed portion of any such payment if the
90    contractor or subcontractor notifies the party whose payment is
91    disputed, in writing, of the amount in dispute and the actions
92    required to cure the dispute. The contractor or subcontractor
93    must pay all undisputed amounts due within the time limits
94    imposed by this section.
95          (7)(a) A local governmental entity must present to the
96    vendor a final punch list of all items required to render
97    complete, satisfactory, and acceptable the construction services
98    purchased within 30 days after the earliest of the following:
99          1. Issuance of a temporary or final certificate of
100    occupancy, if applicable;
101          2. Substantial completion of the construction services
102    purchased, as defined in the contract; or
103          3. Beneficial occupancy or use of the structure, building,
104    facility, or improvement that is the subject of the construction
105    services purchased, as defined in the contract.
106          (b) If the purchase relates to construction services on
107    more than one building or structure, the local governmental
108    entity shall prepare a final punch list for each building or
109    structure. The local governmental entity must present to the
110    vendor a final punch list with regard to each building or
111    structure within 30 days after the earliest of the following:
112          1. Issuance of a temporary or final certificate of
113    occupancy on the particular building or structure, if
114    applicable;
115          2. Substantial completion of the particular building or
116    structure, as defined in the contract; or
117          3. Beneficial occupancy or use of the particular
118    structure, building, facility, or improvement as defined in the
119    contract.
120         
121          Unless the contract provides otherwise, the local governmental
122    entity shall pay out retainage to the vendor based upon the
123    value of the construction services rendered with regard to that
124    structure, building, facility, or improvement as compared to the
125    total value of the purchase.
126          (c) Upon completion of all items on the final punch list,
127    or within 30 days after issuance of the punch list, whichever
128    occurs sooner, the vendor shall submit a payment request for the
129    appropriate amount of retainage. The owner may withhold up to
130    150 percent of the cost to complete any incomplete final punch
131    list items. Thereafter, this act applies to the payment of any
132    payment request for retainage.
133          (d) If the local governmental entity fails to present to
134    the vendor a final punch list within the time periods provided
135    in paragraph (a) or paragraph (b), the project is considered to
136    be complete and the vendor shall submit a payment request for
137    the appropriate amount of retainage. Thereafter, this act
138    applies to the payment of any payment request for retainage.
139          (e) All items that require correction under the contract
140    and that are identified after the preparation and delivery of
141    the final punch list must be considered warranty items or make-
142    good items, and such items have no effect on the final payment
143    of retainage provided in this section.
144          (8)(a) From the commencement of a local government
145    construction project that is subject to this act until 50
146    percent of the contract value has been earned, a local
147    governmental entity may not withhold as retainage more than 10
148    percent of each progress payment to the vendor. When 50 percent
149    of the contract value has been earned, the vendor may submit a
150    payment request to the local governmental entity for up to one-
151    half of the retainage withheld up to that time.
152          (b) After 50 percent of the contract value has been
153    earned, the local governmental entity may not withhold as
154    retainage more than 5 percent of each progress payment to the
155    vendor. However, the vendor may withhold retainage from payments
156    to its subcontractors at a rate higher than 5 percent. The
157    specific amount to be withheld must be determined on a case-by-
158    case basis and must be based on the vendor's assessment of the
159    subcontractor's past performance, the likelihood that such
160    performance will continue, and the vendor's ability to rely on
161    other safeguards. The vendor shall notify the subcontractor, in
162    writing, of its determination to withhold more than 5 percent of
163    the progress payment and the reasons for making that
164    determination.
165          (c) This section does not require the payment or release
166    of amounts that are the subject of a good-faith dispute.
167          (d) This act applies to the payment of any payment request
168    for retainage.
169          Section 4. Section 255.0705, Florida Statutes, is created
170    to read:
171          255.0705 Popular name.--Sections 255.0705-255.078 shall be
172    known by the popular name the "Florida Prompt Payment Act."
173          Section 5. Subsections (2) and (3) of section 255.071,
174    Florida Statutes, are amended to read:
175          255.071 Payment of subcontractors, sub-subcontractors,
176    materialmen, and suppliers on construction contracts for public
177    projects.--
178          (2) The failure to pay any undisputed obligations for such
179    labor, services, or materials within 30 days after the date the
180    labor, services, or materials were furnished and payment for
181    such labor, services, or materials became due, or within 1030
182    days after the date payment for such labor, services, or
183    materials is received, whichever last occurs, shall entitle any
184    person providing such labor, services, or materials to the
185    procedures specified in subsection (3) and the remedies provided
186    in subsection (4).
187          (3) Any person providing labor, services, or materials for
188    the construction of a public building, for the prosecution and
189    completion of a public work, or for repairs upon a public
190    building or public work improvements to real property may file a
191    verified complaint alleging:
192          (a) The existence of a contract for providing such labor,
193    services, or materials to improve real property.
194          (b) A description of the labor, services, or materials
195    provided and alleging that the labor, services, or materials
196    were provided in accordance with the contract.
197          (c) The amount of the contract price.
198          (d) The amount, if any, paid pursuant to the contract.
199          (e) The amount that remains unpaid pursuant to the
200    contract and the amount thereof that is undisputed.
201          (f) That the undisputed amount has remained due and
202    payable pursuant to the contract for more than 30 days after the
203    date the labor or services were accepted or the materials were
204    received.
205          (g) That the person against whom the complaint was filed
206    has received payment on account of the labor, services, or
207    materials described in the complaint more than 1030days prior
208    to the date the complaint was filed.
209          Section 6. Section 255.072, Florida Statutes, is created
210    to read:
211          255.072 Definitions.--As used in ss. 255.073-255.078, the
212    term:
213          (1) "Agent" means project architect, project engineer, or
214    any other agency or person acting on behalf of a public entity.
215          (2) "Construction services" means all labor, services, and
216    materials provided in connection with the construction,
217    alteration, repair, demolition, reconstruction, or any other
218    improvements to real property. The term "construction services"
219    does not include contracts or work performed for the Department
220    of Transportation.
221          (3) "Payment request" means an invoice or request for
222    payment for construction services that conforms with all
223    statutory requirements and with all requirements specified by
224    the public entity to which the payment request is submitted.
225          (4) "Public entity" means the state, a state university,
226    or any office, board, bureau, commission, department, branch,
227    division, or institution thereof, or any project supported by
228    state funds. The term does not include a local governmental
229    entity as defined in s. 218.72(2).
230          (5) "Purchase" means the purchase of construction
231    services.
232          (6) "Vendor" means any person providing construction
233    services to a public entity.
234          Section 7. Section 255.073, Florida Statutes, is created
235    to read:
236          255.073 Timely payment for purchases of construction
237    services.--
238          (1) Except as otherwise provided in ss. 255.072-255.078,
239    s. 215.422 governs the timely payment for construction services
240    by a public entity under this act.
241          (2) If a public entity disputes a portion of a payment
242    request, the undisputed portion must be timely paid in
243    accordance with subsection (1).
244          (3) When a vendor receives payment from a public entity
245    for labor, services, or materials furnished by subcontractors
246    and suppliers hired by the vendor, the vendor shall remit
247    payment due to those subcontractors and suppliers within 10 days
248    after the vendor's receipt of payment. When a subcontractor
249    receives payment from a vendor for labor, services, or materials
250    furnished by subcontractors and suppliers hired by the
251    subcontractor, the subcontractor shall remit payment due to
252    those subcontractors and suppliers within 10 days after the
253    subcontractor's receipt of payment. This subsection does not
254    prohibit a vendor or subcontractor from disputing, pursuant to
255    the terms of the relevant contract, all or any portion of a
256    payment alleged to be due to another party. If such a dispute
257    occurs, the vendor or subcontractor may withhold the disputed
258    portion of any such payment if the vendor or subcontractor
259    notifies the party whose payment is disputed, in writing, of the
260    amount in dispute and the actions required to cure the dispute.
261    The vendor or subcontractor must pay all undisputed amounts due
262    within the time limits imposed by this section.
263          (4) All payments due under this section and not made
264    within the time periods specified by this section shall bear
265    interest at the rate of 1 percent per month, or the rate
266    specified by contract, whichever is greater.
267          Section 8. Section 255.074, Florida Statutes, is created
268    to read:
269          255.074 Procedures for calculation of payment due dates.--
270          (1) Each public entity shall establish procedures whereby
271    each payment request received by the public entity is marked as
272    received on the date on which it is delivered to an agent or
273    employee of the public entity or of a facility or office of the
274    public entity.
275          (2) If the terms under which a purchase is made allow for
276    partial deliveries and a payment request is submitted for a
277    partial delivery, the time for payment for the partial delivery
278    must be calculated from the time of the partial delivery and the
279    submission of the payment request in the same manner as provided
280    in s. 255.073.
281          (3) The public entity must submit a payment request to the
282    Chief Financial Officer for payment no more than 25 days after
283    receipt of the payment request.
284          Section 9. Section 255.075, Florida Statutes, is created
285    to read:
286          255.075 Mandatory interest.--A contract between a public
287    entity and a vendor or a provider of construction services may
288    not prohibit the collection of late payment interest charges
289    allowable under ss. 255.072-255.078.
290          Section 10. Section 255.076, Florida Statutes, is created
291    to read:
292          255.076 Improper payment request; resolution of
293    disputes.--
294          (1) If a vendor submits an improper payment request, the
295    public entity shall, within 10 days after receiving the improper
296    payment request, notify the vendor that the payment request is
297    improper and indicate what corrective action on the part of the
298    vendor is needed to make the payment request proper.
299          (2) If a dispute occurs between a vendor and a public
300    entity concerning payment of a payment request, the dispute must
301    be resolved as provided in this section. Each public entity
302    shall establish a dispute resolution procedure to be followed by
303    the public entity if such a dispute occurs. The procedure must
304    provide that proceedings to resolve the dispute must commence no
305    later than 45 days after the date on which the public entity
306    received the payment request and must conclude by final decision
307    of the public entity no later than 60 days after the date on
308    which the public entity received the payment request. Such
309    procedures are not subject to chapter 120 and do not constitute
310    an administrative proceeding that prohibits a court from
311    deciding de novo any action arising out of the dispute. If the
312    dispute is resolved in favor of the public entity, interest
313    charges begin to accrue 15 days after the public entity's final
314    decision. If the dispute is resolved in favor of the vendor,
315    interest begins to accrue as of the original date the payment
316    became due.
317          (3) In an action to recover amounts due under ss. 255.072-
318    255.078, the court shall award court costs and reasonable
319    attorney's fees, including fees incurred through any appeal, to
320    the prevailing party if the court finds that the nonprevailing
321    party withheld any portion of the payment that is the subject of
322    the action without any reasonable basis in law or fact to
323    dispute the prevailing party's claim to those amounts.
324          Section 11. Section 255.077, Florida Statutes, is created
325    to read:
326          255.077 Project closeout and payment of retainage.--
327          (1) A public entity must present to the vendor a final
328    punch list of all items required to render complete,
329    satisfactory, and acceptable the construction services purchased
330    within 30 days after the earliest of the following:
331          (a) Issuance of a temporary or final certificate of
332    occupancy, if applicable;
333          (b) Substantial completion of the construction services
334    purchased, as defined in the contract; or
335          (c) Beneficial occupancy or use of the structure,
336    building, facility, or improvement that is the subject of the
337    construction services purchased, as defined in the contract.
338          (2) If the purchase relates to construction services on
339    more than one building or structure, the public entity shall
340    prepare a final punch list for each building or structure. The
341    public entity must present to the vendor a final punch list with
342    regard to each building or structure within 30 days after the
343    earliest of the following:
344          (a) Issuance of a temporary or final certificate of
345    occupancy on the particular building or structure, if
346    applicable;
347          (b) Substantial completion of the particular building or
348    structure, as defined in the contract; or
349          (c) Beneficial occupancy or use of the particular
350    structure, building, facility, or improvement as defined in the
351    contract.
352         
353          Unless the contract provides otherwise, the public entity shall
354    pay out retainage to the vendor based upon the value of the
355    construction services rendered with regard to that structure,
356    building, facility, or improvement as compared to the total
357    value of the purchase.
358          (3) Upon completion of all items on the final punch list
359    or within 30 days after issuance of the punch list, whichever
360    occurs sooner, the vendor shall submit a payment request for the
361    appropriate amount of retainage. The owner may withhold up to
362    150 percent of the cost to complete any incomplete final punch
363    list items. Thereafter, ss. 255.072-255.076 apply to the payment
364    of any payment request for retainage.
365          (4) If the public entity fails to present to the vendor a
366    final punch list within the time period provided in subsection
367    (1) or subsection (2), the project is considered to be complete
368    and the vendor shall submit a payment request for the
369    appropriate amount of retainage. Thereafter, ss. 255.072-255.076
370    apply to the payment of any payment request for retainage.
371          (5) All items that require correction under the contract
372    that are identified subsequent to preparation and delivery of
373    the final punch list must be considered warranty items or make-
374    good items, and such items have no effect on the final payment
375    of retainage provided in this section.
376          Section 12. Section 255.078, Florida Statutes, is created
377    to read:
378          255.078 Public construction retainage.--
379          (1) From the commencement of a public construction project
380    that is subject to ss. 255.072-255.078 until 50 percent of the
381    contract value has been earned, a public entity may not withhold
382    as retainage more than 10 percent of each progress payment to
383    the vendor. When 50 percent of the contract value has been
384    earned, the vendor may submit a payment request to the public
385    entity for up to one-half of the retainage withheld up to that
386    time.
387          (2) After 50 percent of the contract value has been
388    earned, the public entity may not withhold as retainage more
389    than 5 percent of each progress payment to the vendor. However,
390    the vendor may withhold retainage from payments to its
391    subcontractors at a rate higher than 5 percent. The specific
392    amount to be withheld must be determined on a case-by-case basis
393    and must be based on the vendor's assessment of the
394    subcontractor's past performance, the likelihood that such
395    performance will continue, and the vendor's ability to rely on
396    other safeguards. The vendor shall notify the subcontractor, in
397    writing, of its determination to withhold more than 5 percent of
398    the progress payment and the reasons for making that
399    determination.
400          (3) This section does not require the payment or release
401    of amounts that are the subject of a good faith dispute.
402          (4) Sections 255.072-255.076 apply to the payment of any
403    payment request for retainage.
404          Section 13. Paragraph (a) of subsection (2) of section
405    255.05, Florida Statutes, is amended, and subsections (10),
406    (11), (12), and (13) are added to said section, to read:
407          255.05 Bond of contractor constructing public buildings;
408    form; action by materialmen.--
409          (2)(a)1. If a claimant is no longer furnishing labor,
410    services, or materials on a project, a contractor or the
411    contractor's agent or attorney may elect to shorten the
412    prescribed time in this paragraph within which an action to
413    enforce any claim against a payment bond provided pursuant to
414    this section may be commenced by recording in the clerk's office
415    a notice in substantially the following form:
416         
417 NOTICE OF CONTEST OF CLAIM
418 AGAINST PAYMENT BOND
419         
420          To: . . . (Name and address of claimant) . . .
421         
422          You are notified that the undersigned contests your notice
423    of nonpayment, dated ____________, ________, and served on the
424    undersigned on ____________, ________, and that the time within
425    which you may file suit to enforce your claim is limited to 60
426    days after the date of service of this notice.
427         
428          DATED on ____________, ________.
429         
430         
431          Signed: . . . (Contractor or Attorney) . . .
432         
433          The claim of any claimant upon whom such notice is served and
434    who fails to institute a suit to enforce his or her claim
435    against the payment bond within 60 days after service of such
436    notice shall be extinguished automatically. The clerk shall mail
437    a copy of the notice of contest to the claimant at the address
438    shown in the notice of nonpayment or most recent amendment
439    thereto and shall certify to such service on the face of such
440    notice and record the notice. Service is complete upon mailing.
441          2. A claimant, except a laborer, who is not in privity
442    with the contractor shall, before commencing or not later than
443    45 days after commencing to furnish labor, materials, or
444    supplies for the prosecution of the work, furnish the contractor
445    with a notice that he or she intends to look to the bond for
446    protection. A claimant who is not in privity with the contractor
447    and who has not received payment for his or her labor,
448    materials, or supplies shall deliver to the contractor and to
449    the surety written notice of the performance of the labor or
450    delivery of the materials or supplies and of the nonpayment. The
451    notice of nonpayment may be served at any time during the
452    progress of the work or thereafter but not before 45 days after
453    the first furnishing of labor, services, or materials, and not
454    later than 90 days after the final furnishing of the labor,
455    services, or materials by the claimant or, with respect to
456    rental equipment, not later than 90 days after the date that the
457    rental equipment was last on the job site available for use. Any
458    notice of nonpayment served by a claimant who is not in privity
459    with the contractor that includes sums for retainage must
460    specify the portion of the amount claimed for retainage.No
461    action for the labor, materials, or supplies may be instituted
462    against the contractor or the surety unless both notices have
463    been given. Notices required or permitted under this section may
464    be served in accordance with s. 713.18. An action, except for an
465    action exclusively for recovery of retainage, must be instituted
466    against the contractor or the surety on the payment bond or the
467    payment provisions of a combined payment and performance bond
468    within 1 year after the performance of the labor or completion
469    of delivery of the materials or supplies. An action exclusively
470    for recovery of retainage must be instituted against the
471    contractor or the surety within 1 year after the performance of
472    the labor or completion of delivery of the materials or
473    supplies, or within 90 days after receipt of final payment (or
474    the payment estimate containing the owner's final reconciliation
475    of quantities if no further payment is earned and due as a
476    result of deductive adjustments) by the contractor or surety,
477    whichever comes last. A claimant may not waive in advance his or
478    her right to bring an action under the bond against the surety.
479    In any action brought to enforce a claim against a payment bond
480    under this section, the prevailing party is entitled to recover
481    a reasonable fee for the services of his or her attorney for
482    trial and appeal or for arbitration, in an amount to be
483    determined by the court, which fee must be taxed as part of the
484    prevailing party's costs, as allowed in equitable actions. The
485    time periods for service of a notice of nonpayment or for
486    bringing an action against a contractor or a surety shall be
487    measured from the last day of furnishing labor, services, or
488    materials by the claimant and shall not be measured by other
489    standards, such as the issuance of a certificate of occupancy or
490    the issuance of a certificate of substantial completion.
491          (10) Notwithstanding any other provision of law to the
492    contrary, a claimant may not institute an action for the sole
493    purpose of recovery of retainage against the contractor or
494    against the surety issuing a payment or performance bond
495    pursuant to this section until:
496          (a) The public entity has paid out that retainage to the
497    contractor and the time provided under ss. 218.70-218.76 or ss.
498    255.072-255.078 for payment of that retainage to the claimant
499    has expired; or
500          (b) The claimant has completed all work under its contract
501    and, if the contractor submitted its final payment request in
502    accordance with this act, 60 days have passed since the owner's
503    receipt of the contractor's final payment request.
504          (11) An owner shall furnish in writing to a claimant who
505    has provided labor, services, or materials to a project, within
506    5 business days after receipt of a written request from that
507    claimant, the following information:
508          (a) The dates of all payment requests received by the
509    owner from the contractor.
510          (b) The dates of all payments made by the owner to the
511    contractor.
512          (c) Whether the owner has received the contractor's final
513    payment request and, if so, the date the final payment request
514    was submitted by the contractor to the owner.
515          (12) The owner has a duty to notify all claimants of
516    record for the project, in writing, that the final payment has
517    been made to the contractor or, if no further payment is earned
518    by the contractor, a statement that no further payment will be
519    made voluntarily by the owner to the contractor and the date on
520    which the owner provided the contractor with the owner's final
521    reconciliation of quantities. The notice to claimants must be
522    made in writing within 5 days after the date final payment is
523    made or the final reconciliation of quantities is given.
524          (13) An owner who fails to furnish any information
525    required by this section is liable directly to a claimant for
526    damages sustained as a result of the failure to timely provide
527    the information, plus costs, interest, and attorney's fees.