| 1 | A bill to be entitled | 
| 2 | An act relating to mining and extraction activities; | 
| 3 | amending s. 373.414, F.S.; providing that financial | 
| 4 | responsibility for mitigation for wetlands and other | 
| 5 | surface waters required by a permit for activities | 
| 6 | associated with the extraction of limestone are subject to | 
| 7 | approval by the Department of Environmental Protection as | 
| 8 | part of permit application review; amending s. 378.901, | 
| 9 | F.S.; authorizing mine operators proposing to mine or | 
| 10 | extract limestone to apply for a life-of-the-mine permit; | 
| 11 | authorizing operators of existing mines to apply for a | 
| 12 | life-of-the-mine permit; clarifying the authority of local | 
| 13 | governments to approve, approve with conditions, deny, or | 
| 14 | impose certain permit durations; providing an effective | 
| 15 | date. | 
| 16 | 
 | 
| 17 | Be It Enacted by the Legislature of the State of Florida: | 
| 18 | 
 | 
| 19 | Section 1.  Paragraph (a) of subsection (19) of section | 
| 20 | 373.414, Florida Statutes, is amended to read: | 
| 21 | 373.414  Additional criteria for activities in surface | 
| 22 | waters and wetlands.- | 
| 23 | (19)(a)  Financial responsibility for mitigation for | 
| 24 | wetlands and other surface waters required by a permit issued | 
| 25 | pursuant to this part for activities associated with the | 
| 26 | extraction of limestone and phosphate are subject to approval by | 
| 27 | the department as part of permit application review. Financial | 
| 28 | responsibility for permitted activities which will occur over a | 
| 29 | period of 3 years or less of mining operations must be provided | 
| 30 | to the department prior to the commencement of mining operations | 
| 31 | and shall be in an amount equal to 110 percent of the estimated | 
| 32 | mitigation costs for wetlands and other surface waters affected | 
| 33 | under the permit. For permitted activities which will occur over | 
| 34 | a period of more than 3 years of mining operations, the initial | 
| 35 | financial responsibility demonstration shall be in an amount | 
| 36 | equal to 110 percent of the estimated mitigation costs for | 
| 37 | wetlands and other surface waters affected in the first 3 years | 
| 38 | of operation under the permit; and, for each year thereafter, | 
| 39 | the financial responsibility demonstration shall be updated, | 
| 40 | including to provide an amount equal to 110 percent of the | 
| 41 | estimated mitigation costs for the next year of operations under | 
| 42 | the permit for which financial responsibility has not already | 
| 43 | been demonstrated and to release portions of the financial | 
| 44 | responsibility mechanisms in accordance with applicable rules. | 
| 45 | Section 2.  Subsection (2) of section 378.901, Florida | 
| 46 | Statutes, is amended to read: | 
| 47 | 378.901  Life-of-the-mine permit.- | 
| 48 | (2)  As an alternative to, and in lieu of, separate | 
| 49 | applications for permits required by part IV of chapter 373 and | 
| 50 | part IV of this chapter, each operator who proposes to mine or | 
| 51 | extract heavy minerals, limestone, or fuller's earth clay or the | 
| 52 | operator of an existing mine may apply to the bureau for a life- | 
| 53 | of-the-mine permit. Nothing in this subsection limits or | 
| 54 | restricts the authority of a local government to approve, | 
| 55 | approve with conditions, deny, or impose a permit duration | 
| 56 | different from the duration of a permit issued pursuant to this | 
| 57 | section. | 
| 58 | Section 3.  This act shall take effect upon becoming a law. |