Florida Senate - 2026                        COMMITTEE AMENDMENT
       Bill No. CS for SB 1138
       
       
       
       
       
       
                                Ì249874UÎ249874                         
       
                              LEGISLATIVE ACTION                        
                    Senate             .             House              
                                       .                                
                                       .                                
                                       .                                
                                       .                                
                                       .                                
       —————————————————————————————————————————————————————————————————




       —————————————————————————————————————————————————————————————————
       The Committee on Rules (Massullo) recommended the following:
       
    1         Senate Amendment (with title amendment)
    2  
    3         Delete everything after the enacting clause
    4  and insert:
    5         Section 1. Section 125.022, Florida Statutes, is amended to
    6  read:
    7         125.022 Development permits and orders; development
    8  preapplication consulting services program required.—
    9         (1)(a)By January 1, 2027, each county with a population of
   10  75,000 or greater shall create and implement a program for the
   11  purpose of making available development preapplication
   12  consultation services at an applicant’s request. This subsection
   13  may not be construed to affect or require the modification of a
   14  county program that makes available the same or substantially
   15  similar development preapplication consulting services to an
   16  applicant for a development permit or development order,
   17  including a program that requires mandatory preapplication
   18  meetings for specified types of developments, if such county
   19  program exists on or before July 1, 2026.
   20         1.The preapplication consultation services authorized in
   21  this subsection are limited to those applications for permits as
   22  defined in s. 163.3169.
   23         2.The county may use a qualified contractor or a qualified
   24  contractor firm as defined in s. 163.3169 to fulfill the
   25  preapplication consultation services required in this
   26  subsection.
   27         (b)A development preapplication consultation services
   28  program must, at minimum, provide all of the following:
   29         1.The minimum information that must be submitted in an
   30  application for a permit as defined in s. 163.3169.
   31         2.The review and precertification of completeness of the
   32  application and all related documents, including site
   33  engineering plans or site plans or their functional equivalent,
   34  or plats, and their compliance with all relevant existing land
   35  development regulations.
   36         (c)If an applicant chooses to use the development
   37  preapplication consultation services program, the county, upon
   38  receipt of the proposed development application, shall confirm
   39  receipt, verify completeness, and issue a written notification
   40  to the applicant indicating that all required information has
   41  been submitted, or specify in writing with particularity any
   42  deficiencies in the application, within 5 business days. If the
   43  application is deficient, the applicant has 30 days to address
   44  the deficiencies by submitting the required additional
   45  information. If the county fails to issue the written
   46  notification within 5 business days, the application is deemed
   47  complete by operation of law without conditions, and the county
   48  must process the application as required in paragraph (d).
   49         (d)1.Upon receipt of the applicant’s completed
   50  application, the county must process the application for final
   51  action and must approve, approve with conditions, or deny the
   52  application within 45 days after submission of a complete
   53  application, except the county may not review again those plans
   54  specified in subparagraph (b)2.
   55         2.If the county fails to take final action to approve,
   56  approve with conditions, or deny the application within 45 days,
   57  the applicant shall notify the county in writing and if the
   58  county fails to respond within 10 days, the application is
   59  deemed approved by operation of law without conditions, and the
   60  applicant is entitled to proceed with the proposed activity or
   61  development as though the county had granted unconditional
   62  approval. Approval pursuant to this subparagraph may not be
   63  construed to relieve the applicant of the obligation to comply
   64  with all other applicable federal, state, and local laws,
   65  regulations, and ordinances.
   66         (2)If an applicant for a development permit or development
   67  order is not eligible, does not request, or elects not to use
   68  the county’s development preapplication consulting services
   69  program pursuant to subsection (1), all of the following
   70  requirements shall apply:
   71         (a)(1) A county shall specify in writing the minimum
   72  information that must be submitted in an application for a
   73  zoning approval, rezoning approval, subdivision approval,
   74  certification, special exception, or variance. A county shall
   75  make the minimum information available for inspection and
   76  copying at the location where the county receives applications
   77  for development permits and orders, provide the information to
   78  the applicant at a preapplication meeting, or post the
   79  information on the county’s website.
   80         (b)1.(2) Within 5 business days after receiving an
   81  application for approval of a development permit or development
   82  order, a county shall confirm receipt of the application using
   83  contact information provided by the applicant. Within 30 days
   84  after receiving an application for approval of a development
   85  permit or development order, a county must review the
   86  application for completeness and issue a written notification to
   87  the applicant indicating that all required information is
   88  submitted or specify in writing with particularity any areas
   89  that are deficient. If the application is deficient, the
   90  applicant has 30 days to address the deficiencies by submitting
   91  the required additional information.
   92         2. For applications that do not require final action
   93  through a quasi-judicial hearing or a public hearing, the county
   94  must approve, approve with conditions, or deny the application
   95  for a development permit or development order within 120 days
   96  after the county has deemed the application complete.
   97         3. For applications that require final action through a
   98  quasi-judicial hearing or a public hearing, the county must
   99  approve, approve with conditions, or deny the application for a
  100  development permit or development order within 180 days after
  101  the county has deemed the application complete.
  102         4. Both parties may agree in writing or in a public meeting
  103  or hearing to an extension of time, particularly in the event of
  104  a force majeure or other extraordinary circumstance. An
  105  approval, approval with conditions, or denial of the application
  106  for a development permit or development order must include
  107  written findings supporting the county’s decision.
  108  
  109  The timeframes contained in this paragraph subsection do not
  110  apply in an area of critical state concern, as designated in s.
  111  380.0552. The timeframes contained in this paragraph subsection
  112  restart if an applicant makes a substantive change to the
  113  application. As used in this paragraph subsection, the term
  114  “substantive change” means an applicant-initiated change of 15
  115  percent or more in the proposed density, intensity, or square
  116  footage of a parcel.
  117         (c)1.(3)(a) When reviewing an application for a development
  118  permit or development order that is certified by a professional
  119  listed in s. 403.0877, a county may not request additional
  120  information from the applicant more than three times, unless the
  121  applicant waives the limitation in writing.
  122         2.(b) If a county makes a request for additional
  123  information and the applicant submits the required additional
  124  information within 30 days after receiving the request, the
  125  county must review the application for completeness and issue a
  126  letter indicating that all required information has been
  127  submitted or specify with particularity any areas that are
  128  deficient within 30 days after receiving the additional
  129  information.
  130         3.(c) If a county makes a second request for additional
  131  information and the applicant submits the required additional
  132  information within 30 days after receiving the request, the
  133  county must review the application for completeness and issue a
  134  letter indicating that all required information has been
  135  submitted or specify with particularity any areas that are
  136  deficient within 10 days after receiving the additional
  137  information.
  138         4.(d) Before a third request for additional information,
  139  the applicant must be offered a meeting to attempt to resolve
  140  outstanding issues. If a county makes a third request for
  141  additional information and the applicant submits the required
  142  additional information within 30 days after receiving the
  143  request, the county must deem the application complete within 10
  144  days after receiving the additional information or proceed to
  145  process the application for approval or denial unless the
  146  applicant waived the county’s limitation in writing as described
  147  in subparagraph 1. paragraph (a).
  148         5.(e) Except as provided in subsection (4) subsection (7),
  149  if the applicant believes the request for additional information
  150  is not authorized by ordinance, rule, statute, or other legal
  151  authority, the county, at the applicant’s request, shall proceed
  152  to process the application for approval or denial.
  153         (d)(4) A county must issue a refund to an applicant equal
  154  to:
  155         1.(a) Ten percent of the application fee if the county
  156  fails to issue written notification of completeness or written
  157  specification of areas of deficiency within 30 days after
  158  receiving the application.
  159         2.(b) Ten percent of the application fee if the county
  160  fails to issue a written notification of completeness or written
  161  specification of areas of deficiency within 30 days after
  162  receiving the additional information pursuant to subparagraph
  163  (c)2. paragraph (3)(b).
  164         3.(c) Twenty percent of the application fee if the county
  165  fails to issue a written notification of completeness or written
  166  specification of areas of deficiency within 10 days after
  167  receiving the additional information pursuant to subparagraph
  168  (c)3. paragraph (3)(c).
  169         4.(d) Fifty percent of the application fee if the county
  170  fails to approve, approves with conditions, or denies the
  171  application within 30 days after conclusion of the 120-day
  172  timeframe specified in subparagraph (b)2. or the 180-day
  173  timeframe specified in subparagraph (b)3. subsection (2).
  174         5.(e) One hundred percent of the application fee if the
  175  county fails to approve, approves with conditions, or denies an
  176  application 31 days or more after conclusion of the 120-day
  177  timeframe specified in subparagraph (b)2. or the 180-day
  178  timeframe specified in subparagraph (b)3. subsection (2).
  179  
  180  A county is not required to issue a refund if the applicant and
  181  the county agree to an extension of time, the delay is caused by
  182  the applicant, or the delay is attributable to a force majeure
  183  or other extraordinary circumstance.
  184         (e)(5) When a county denies an application for a
  185  development permit or development order, the county shall give
  186  written notice to the applicant. The notice must include a
  187  citation to the applicable portions of an ordinance, rule,
  188  statute, or other legal authority for the denial of the permit
  189  or order.
  190         (3)(6) As used in this section, the terms “development
  191  permit” and “development order” have the same meaning as in s.
  192  163.3164, but do not include building permits.
  193         (4)(7) For any development permit application filed with
  194  the county after July 1, 2012, a county may not require as a
  195  condition of processing or issuing a development permit or
  196  development order that an applicant obtain a permit or approval
  197  from any state or federal agency unless the agency has issued a
  198  final agency action that denies the federal or state permit
  199  before the county action on the local development permit.
  200         (5)(8) Issuance of a development permit or development
  201  order by a county does not in any way create any rights on the
  202  part of the applicant to obtain a permit from a state or federal
  203  agency and does not create any liability on the part of the
  204  county for issuance of the permit if the applicant fails to
  205  obtain requisite approvals or fulfill the obligations imposed by
  206  a state or federal agency or undertakes actions that result in a
  207  violation of state or federal law. A county shall attach such a
  208  disclaimer to the issuance of a development permit and shall
  209  include a permit condition that all other applicable state or
  210  federal permits be obtained before commencement of the
  211  development.
  212         (6)(9) This section does not prohibit a county from
  213  providing information to an applicant regarding what other state
  214  or federal permits may apply.
  215         Section 2. Section 163.3169, Florida Statutes, is created
  216  to read:
  217         163.3169 Using qualified contractors in development order
  218  preapplication review.—
  219         (1)DEFINITIONS.—As used in this section, the term:
  220         (a) “Applicant” means a person or legal entity having a
  221  legal or equitable ownership interest in real property, or an
  222  authorized agent acting on behalf of such person or entity,
  223  which applies for a land development approval from the local
  224  government pursuant to this section.
  225         (b)“Application” means a properly completed and submitted
  226  request for a permit, as defined herein, on behalf of an
  227  applicant which includes an affidavit from a qualified
  228  contractor as required by this section. The term does not
  229  include plans or permits as reviewed under s. 553.791.
  230         (c)“Conflict of interest” has the same meaning as in s.
  231  112.312 and includes conflicts of interest recognized under
  232  applicable licensing or certification standards applicable to
  233  the qualified contractor.
  234         (d)“Development services office” means the entity, office,
  235  division, or department of a local government which is
  236  responsible for reviewing applications for compliance with the
  237  local government’s land development regulations and other
  238  applicable federal, state, and local requirements. This office
  239  may be substantively identical to or housed within the local
  240  government’s planning and zoning department.
  241         (e)“Development services official” means the individual in
  242  the development services office of the governing jurisdiction
  243  who is responsible for the direct regulatory administration or
  244  supervision of the review and approval process required to
  245  indicate compliance with applicable land development
  246  regulations. The term includes any duly authorized designee of
  247  such person. This individual may be the executive director of
  248  the governing body of a local government or the division
  249  director of the local government’s planning and zoning
  250  department.
  251         (f) “Final plat” has the same meaning as in s. 177.073.
  252         (g)“Governing body” has the same meaning as in s.
  253  163.3164.
  254         (h)“Land development regulations” has the same meaning as
  255  in s. 163.3164, but excludes building permits and plans subject
  256  to s. 553.791.
  257         (i)“Local government” means:
  258         1.A county that has 75,000 or more residents, but does not
  259  include a county subject to s. 380.0552; or
  260         2.A municipality that has 10,000 or more residents.
  261         (j) “Permit” means an authorization, approval, or grant by
  262  a local governing body which authorizes the development of land
  263  for any site plan or development plan approval, or any
  264  subdivision approval, as defined in this section.
  265         (k)“Plans” has the same meaning as in s. 177.073.
  266         (l)“Plat or replat” has the same meaning as in s.
  267  177.031(14).
  268         (m) “Preapplication review” means the analysis of a permit
  269  conducted by a qualified contractor to ensure compliance with a
  270  comprehensive plan, chapter 177, and applicable land development
  271  regulations, and which is part of the application as authorized
  272  under this section.
  273         (n)“Preliminary plat” has the same meaning as in 177.073.
  274         (o) “Qualified contractor” means the individual or firm
  275  that has demonstrated knowledge of and experience with the types
  276  of permits or development approvals specified in this section.
  277  The term includes, but is not limited to, any of the following:
  278         1.An engineer or engineering firm licensed under chapter
  279  471.
  280         2.A surveyor or mapper, or a surveyor’s or mapper’s firm,
  281  licensed under chapter 472.
  282         3.An architect or architecture firm licensed under part I
  283  of chapter 481.
  284         4.A landscape architect or a landscape architecture firm
  285  registered under part II of chapter 481.
  286         5.A planner certified by the American Institute of
  287  Certified Planners with at least 5 years of relevant government
  288  experience or at least 10 years of experience as an urban
  289  planner if not certified.
  290         (p)“Qualified contractor firm” means a business
  291  organization, including a corporation, partnership, business
  292  trust, or other legal entity, which offers services under this
  293  section to the public through licensees who act as agents,
  294  employees, officers, or partners of the firm. A person who is
  295  licensed as an engineer under chapter 471; a surveyor or mapper
  296  licensed under chapter 472; an architect licensed under part I
  297  of chapter 481; a landscape architect licensed under part II of
  298  chapter 481; or who is certified by the American Institute of
  299  Certified Planners with at least 5 years of relevant government
  300  experience, or at least 10 years of relevant experience as an
  301  urban planner if not certified, may act as a qualified
  302  contractor for an agent, employee, or officer of the qualified
  303  contractor firm.
  304         (q)“Site plan or development plan approval” means a site
  305  development proposal, or its functional equivalent, including a
  306  modification to an existing development approval, which is
  307  expressly designated by the local government for administrative
  308  review and approval by local government staff or a designated
  309  administrative official, without the requirement of approval by
  310  an appointed review board or a governing body and which does not
  311  materially increase density, intensity, traffic, infrastructure
  312  demand, environmental impacts, or significant offsite impacts,
  313  and therefore does not require full site plan review or
  314  discretionary policy review. The term includes approvals or
  315  permits governed by objective, nondiscretionary standards that
  316  are designated by the local government for administrative
  317  approval by local government staff or an administrative official
  318  and which also includes, but is not limited to approvals or
  319  permits related to trees, signs, landscaping, and minor
  320  modifications.
  321         (r)“Subdivision approval” or its functional equivalent,
  322  including a modification, means an administrative review process
  323  applicable to the division of land into a limited number of lots
  324  which does not create new public streets or require significant
  325  public infrastructure improvements and does not materially
  326  increase development impacts. The term applies only to approvals
  327  expressly designated by the local government for administrative
  328  review and approval by local government staff or a designated
  329  administrator without the requirement of approval by an
  330  appointed review board or a governing body. A subdivision
  331  qualifies under this definition if it involves a number of lots
  332  as specified by the local government, complies with all
  333  applicable zoning, dimensional, access utility, and
  334  environmental standards, and can be served by existing public
  335  facilities or approved private systems, allowing the subdivision
  336  to be reviewed for compliance with objective standards of land
  337  development code and approved by local government staff or a
  338  designated administrative official without requiring
  339  discretionary policy determinations.
  340         (2)REGISTRY.—
  341         (a)By January 1, 2027, a local government shall establish
  342  a registry of at least four qualified contractors or two
  343  qualified contractor firms which the governing body shall use to
  344  supplement the local government’s staff resources in ways
  345  determined by the governing body upon the written request by an
  346  applicant for fulfilling:
  347         1.The preapplication consultation services for permits
  348  under s. 125.022(1) and s. 166.033(1);
  349         2.The requirements of s. 177.073 for processing and
  350  expediting the review of an application for a preliminary plat
  351  or any plans related to such application; or
  352         3.The requirements of s. 177.071 requiring the
  353  administrative approval of a plat or replat.
  354         (b)A qualified contractor or a qualified contractor firm
  355  on the registry which is hired pursuant to this section may not
  356  have a conflict of interest. If a prohibitive conflict of
  357  interest exists, the applicant may use an otherwise qualified
  358  contractor.
  359         (c)A local government may enter into an agreement with
  360  another local government for the purpose of using public
  361  employees who meet the requirements for a qualified contractor
  362  to satisfy the minimum numerical requirements for qualified
  363  contractors for the registry. A local government may not add its
  364  own employees to its own registry.
  365         (d)If a local government fails to establish or maintain
  366  the registry, an applicant may, at its sole discretion, retain a
  367  qualified contractor or a qualified contractor firm of the
  368  applicant’s choosing to provide preapplication consultation
  369  services, provided that the selected qualified contractor or
  370  qualified contractor firm does not have a conflict of interest.
  371  If a conflict of interest is identified after selection, the
  372  applicant must promptly replace the qualified contractor or
  373  qualified contractor firm with one that has no conflict of
  374  interest.
  375         (e)The local government may not condition, deny, or delay
  376  the applicant’s selection or use of such qualified contractor or
  377  qualified contractor firm, and the applicant is responsible for
  378  all fees and costs associated with the qualified contractor or
  379  qualified contractor firm used in this manner.
  380         (f)If an applicant uses a qualified contractor or a
  381  qualified contractor firm for such purpose, the local government
  382  must provide access to public records and information reasonably
  383  necessary to perform preapplication consultation services. This
  384  paragraph does not authorize the disclosure of records that are
  385  confidential or exempt from public inspection or copying under
  386  chapter 119 or any other applicable law, and access to such
  387  records is provided only to the extent permitted by law. This
  388  paragraph may not be construed to require a local government to
  389  violate the licensing terms of proprietary software or related
  390  vendor agreements.
  391         Section 3. Section 166.033, Florida Statutes, is amended to
  392  read:
  393         166.033 Development permits and orders; development
  394  preapplication consulting services program required.—
  395         (1)(a)By January 1, 2027, each municipality with a
  396  population of 10,000 or greater shall create and implement a
  397  program for the purpose of making available development
  398  preapplication consultation services at an applicant’s request.
  399  This subsection may not be construed to affect or require the
  400  modification of a municipal program that makes available the
  401  same or substantially similar development preapplication
  402  consulting services to an applicant for a development permit or
  403  development order, including a program that requires mandatory
  404  preapplication meetings for specified types of developments, if
  405  such municipal program exists on or before July 1, 2026.
  406         1. The preapplication consultation services authorized in
  407  this subsection are limited to those applications for permits as
  408  defined in s. 163.3169.
  409         2. The municipality may use a qualified contractor or a
  410  qualified contractor firm as defined in s. 163.3169 to fulfill
  411  the preapplication consultation services required in this
  412  subsection.
  413         (b) A development preapplication consultation services
  414  program must, at minimum, provide all of the following:
  415         1. The minimum information that must be submitted in an
  416  application for a permit as defined in s. 163.3169.
  417         2. The review and precertification of completeness of the
  418  application and all related documents, including site
  419  engineering plans or site plans or their functional equivalent,
  420  or plats, and their compliance with all relevant existing land
  421  development regulations.
  422         (c) If an applicant chooses to use the development
  423  preapplication consultation services program, the municipality,
  424  upon receipt of the proposed development application, shall
  425  confirm receipt, verify completeness, and issue a written
  426  notification to the applicant indicating that all required
  427  information has been submitted, or specify in writing with
  428  particularity any deficiencies within 5 business days. If the
  429  application is deficient, the applicant has 30 days to address
  430  the deficiencies by submitting the required information. If the
  431  municipality fails to issue the written notification within 5
  432  business days, the application is deemed complete by operation
  433  of law without conditions, and the municipality must process the
  434  application as required in paragraph (d).
  435         (d)1. Upon receipt of the applicant’s completed
  436  application, the municipality must process the application for
  437  final action and must approve, approve with conditions, or deny
  438  the application within 45 days after submission of a complete
  439  application, except the municipality may not review again those
  440  plans specified in subparagraph (b)2.
  441         2.If the municipality fails to take final action to
  442  approve, approve with conditions, or deny the application within
  443  the 45 days, the applicant shall notify the municipality in
  444  writing. If the municipality fails to respond within 10 days,
  445  the application is deemed approved by operation of law without
  446  conditions, and the applicant is entitled to proceed with the
  447  proposed activity or development as though the municipality had
  448  granted unconditional approval. Approval pursuant to this
  449  subparagraph may not be construed to relieve the applicant of
  450  the obligation to comply with all other applicable federal,
  451  state, and local laws, regulations, and ordinances.
  452         (2)If an applicant for a development permit or development
  453  order is not eligible, does not request, or elects not to use
  454  the municipality’s development preapplication consulting
  455  services program pursuant to subsection (1), all of the
  456  following requirements shall apply:
  457         (a)(1) A municipality shall specify in writing the minimum
  458  information that must be submitted for an application for a
  459  zoning approval, rezoning approval, subdivision approval,
  460  certification, special exception, or variance. A municipality
  461  shall make the minimum information available for inspection and
  462  copying at the location where the municipality receives
  463  applications for development permits and orders, provide the
  464  information to the applicant at a preapplication meeting, or
  465  post the information on the municipality’s website.
  466         (b)1.(2) Within 5 business days after receiving an
  467  application for approval of a development permit or development
  468  order, a municipality shall confirm receipt of the application
  469  using contact information provided by the applicant. Within 30
  470  days after receiving an application for approval of a
  471  development permit or development order, a municipality must
  472  review the application for completeness and issue a written
  473  notification to the applicant indicating that all required
  474  information is submitted or specify in writing with
  475  particularity any areas that are deficient. If the application
  476  is deficient, the applicant has 30 days to address the
  477  deficiencies by submitting the required additional information.
  478         2. For applications that do not require final action
  479  through a quasi-judicial hearing or a public hearing, the
  480  municipality must approve, approve with conditions, or deny the
  481  application for a development permit or development order within
  482  120 days after the municipality has deemed the application
  483  complete.
  484         3. For applications that require final action through a
  485  quasi-judicial hearing or a public hearing, the municipality
  486  must approve, approve with conditions, or deny the application
  487  for a development permit or development order within 180 days
  488  after the municipality has deemed the application complete.
  489         4. Both parties may agree in writing or in a public meeting
  490  or hearing to an extension of time, particularly in the event of
  491  a force majeure or other extraordinary circumstance. An
  492  approval, approval with conditions, or denial of the application
  493  for a development permit or development order must include
  494  written findings supporting the municipality’s decision.
  495  
  496  The timeframes contained in this paragraph subsection do not
  497  apply in an area of critical state concern, as designated in s.
  498  380.0552 or chapter 28-36, Florida Administrative Code. The
  499  timeframes contained in this paragraph subsection restart if an
  500  applicant makes a substantive change to the application. As used
  501  in this paragraph subsection, the term “substantive change”
  502  means an applicant-initiated change of 15 percent or more in the
  503  proposed density, intensity, or square footage of a parcel.
  504         (c)1.(3)(a) When reviewing an application for a development
  505  permit or development order that is certified by a professional
  506  listed in s. 403.0877, a municipality may not request additional
  507  information from the applicant more than three times, unless the
  508  applicant waives the limitation in writing.
  509         2.(b) If a municipality makes a request for additional
  510  information and the applicant submits the required additional
  511  information within 30 days after receiving the request, the
  512  municipality must review the application for completeness and
  513  issue a letter indicating that all required information has been
  514  submitted or specify with particularity any areas that are
  515  deficient within 30 days after receiving the additional
  516  information.
  517         3.(c) If a municipality makes a second request for
  518  additional information and the applicant submits the required
  519  additional information within 30 days after receiving the
  520  request, the municipality must review the application for
  521  completeness and issue a letter indicating that all required
  522  information has been submitted or specify with particularity any
  523  areas that are deficient within 10 days after receiving the
  524  additional information.
  525         4.(d) Before a third request for additional information,
  526  the applicant must be offered a meeting to attempt to resolve
  527  outstanding issues. If a municipality makes a third request for
  528  additional information and the applicant submits the required
  529  additional information within 30 days after receiving the
  530  request, the municipality must deem the application complete
  531  within 10 days after receiving the additional information or
  532  proceed to process the application for approval or denial unless
  533  the applicant waived the municipality’s limitation in writing as
  534  described in paragraph (a).
  535         5.(e) Except as provided in subsection (4) subsection (7),
  536  if the applicant believes the request for additional information
  537  is not authorized by ordinance, rule, statute, or other legal
  538  authority, the municipality, at the applicant’s request, shall
  539  proceed to process the application for approval or denial.
  540         (d)(4) A municipality must issue a refund to an applicant
  541  equal to:
  542         1.(a) Ten percent of the application fee if the
  543  municipality fails to issue written notification of completeness
  544  or written specification of areas of deficiency within 30 days
  545  after receiving the application.
  546         2.(b) Ten percent of the application fee if the
  547  municipality fails to issue written notification of completeness
  548  or written specification of areas of deficiency within 30 days
  549  after receiving the additional information pursuant to
  550  subparagraph (c)2. paragraph (3)(b).
  551         3.(c) Twenty percent of the application fee if the
  552  municipality fails to issue written notification of completeness
  553  or written specification of areas of deficiency within 10 days
  554  after receiving the additional information pursuant to
  555  subparagraph (c)3. paragraph (3)(c).
  556         4.(d) Fifty percent of the application fee if the
  557  municipality fails to approve, approves with conditions, or
  558  denies the application within 30 days after conclusion of the
  559  120-day timeframe specified in subparagraph (b)2. or the 180-day
  560  timeframe specified in subparagraph (b)3. subsection (2).
  561         5.(e) One hundred percent of the application fee if the
  562  municipality fails to approve, approves with conditions, or
  563  denies an application 31 days or more after conclusion of the
  564  120-day timeframe specified in subparagraph (b)2. or the 180-day
  565  timeframe specified in subparagraph (b)3. subsection (2).
  566  
  567  A municipality is not required to issue a refund if the
  568  applicant and the municipality agree to an extension of time,
  569  the delay is caused by the applicant, or the delay is
  570  attributable to a force majeure or other extraordinary
  571  circumstance.
  572         (e)(5) When a municipality denies an application for a
  573  development permit or development order, the municipality shall
  574  give written notice to the applicant. The notice must include a
  575  citation to the applicable portions of an ordinance, rule,
  576  statute, or other legal authority for the denial of the permit
  577  or order.
  578         (3)(6) As used in this section, the terms “development
  579  permit” and “development order” have the same meaning as in s.
  580  163.3164, but do not include building permits.
  581         (4)(7) For any development permit application filed with
  582  the municipality after July 1, 2012, a municipality may not
  583  require as a condition of processing or issuing a development
  584  permit or development order that an applicant obtain a permit or
  585  approval from any state or federal agency unless the agency has
  586  issued a final agency action that denies the federal or state
  587  permit before the municipal action on the local development
  588  permit.
  589         (5)(8) Issuance of a development permit or development
  590  order by a municipality does not create any right on the part of
  591  an applicant to obtain a permit from a state or federal agency
  592  and does not create any liability on the part of the
  593  municipality for issuance of the permit if the applicant fails
  594  to obtain requisite approvals or fulfill the obligations imposed
  595  by a state or federal agency or undertakes actions that result
  596  in a violation of state or federal law. A municipality shall
  597  attach such a disclaimer to the issuance of development permits
  598  and shall include a permit condition that all other applicable
  599  state or federal permits be obtained before commencement of the
  600  development.
  601         (6)(9) This section does not prohibit a municipality from
  602  providing information to an applicant regarding what other state
  603  or federal permits may apply.
  604         Section 4. Paragraphs (c) and (d) are added to subsection
  605  (1) of section 177.071, Florida Statutes, to read:
  606         177.071 Administrative approval of plats or replats by
  607  designated county or municipal official.—
  608         (1)
  609         (c) A governing body and its designated administrative
  610  authority shall use, upon the written request of the applicant,
  611  the registry established in s. 163.3169 to supplement local
  612  government staff resources in ways determined by the governing
  613  body for processing and expediting the requirements of this
  614  section.
  615         (d)A local government may not create, establish, or apply
  616  any additional local procedure or condition for the
  617  administrative approval of a plat or replat under this section
  618  which is inconsistent with this section or s. 177.091. If
  619  infrastructure financial assurances are required as a condition
  620  of plat or replat approval, the administrative authority
  621  designated in paragraph (a) must receive and act upon the
  622  proposed assurance. The local government shall accept commonly
  623  used forms of financial assurance, including performance bonds,
  624  letters of credit, and escrow agreements, provided that the
  625  assurance is in a form reasonably acceptable to the local
  626  government and issued by a financially responsible issuer
  627  meeting objective, uniformly applied standards. Local government
  628  review of such financial assurance shall be limited to verifying
  629  that the amount, form, and issuer satisfy the requirements of s.
  630  177.091(8) and (9) and the local government’s uniformly applied
  631  standards, and may not be used to unreasonably delay approval.
  632  If the assurance is deficient, the local government must provide
  633  written notice of deficiencies within 10 business days.
  634         Section 5. Paragraph (a) of subsection (1), paragraphs (a)
  635  and (b) of subsection (2), paragraph (a) of subsection (3),
  636  subsection (4), paragraphs (b) and (c) of subsection (6), and
  637  subsection (8) of section 177.073, Florida Statutes, are
  638  amended, and paragraph (d) is added to subsection (2) of that
  639  section, to read:
  640         177.073 Expedited approval of residential building permits
  641  before a final plat is recorded.—
  642         (1) As used in this section, the term:
  643         (a) “Applicant” means a homebuilder or developer who files
  644  an application with the local governing body to identify the
  645  percentage of planned homes, or the number of building permits,
  646  that the local governing body must issue for a residential
  647  subdivision or one or more phases in a multiphased planned
  648  community, subdivision, or planned community.
  649         (2)(a) By October 1, 2024, the governing body of a county
  650  that has 75,000 residents or more and any governing body of a
  651  municipality that has 10,000 residents or more and 25 acres or
  652  more of contiguous land that the local government has designated
  653  in the local government’s comprehensive plan and future land use
  654  map as land that is agricultural or to be developed for
  655  residential purposes shall create a program to expedite the
  656  process for issuing building permits for residential
  657  subdivisions or one or more phases in a multiphased planned
  658  community, subdivision, or planned communities in accordance
  659  with the Florida Building Code and this section before a final
  660  plat is recorded with the clerk of the circuit court. The
  661  expedited process must include an application for an applicant
  662  to identify the percentage of planned homes, not to exceed 50
  663  percent of the residential subdivision or a planned community,
  664  or the number of building permits that the governing body must
  665  issue for the residential subdivision or planned community. The
  666  application or the local government’s final approval may not
  667  alter or restrict the applicant from receiving the number of
  668  building permits requested, so long as the request does not
  669  exceed 50 percent of the planned homes of the residential
  670  subdivision or planned community or the number of building
  671  permits. This paragraph does not:
  672         1. Restrict the governing body from issuing more than 50
  673  percent of the building permits for the residential subdivision
  674  or planned community.
  675         2. Apply to a county subject to s. 380.0552.
  676         (b) Subject to the requirements under paragraph (6)(b), a
  677  governing body that had a program in place before July 1, 2023,
  678  to expedite the building permit process, need only update its
  679  their program to approve an applicant’s written application to
  680  issue up to 50 percent of the building permits for the
  681  residential subdivision or planned community in order to comply
  682  with this section. This paragraph does not restrict a governing
  683  body from issuing more than 50 percent of the building permits
  684  for the residential subdivision or planned community.
  685         (d)1.If a governing body fails to adopt a program under
  686  paragraph (a) or paragraph (c), or fails to update or modify an
  687  existing program as required under paragraph (b), by the
  688  applicable statutory deadline, the following will apply without
  689  further action or approval by the governing body and
  690  notwithstanding any conflicting local requirement:
  691         a.The applicant has an unconditional, self-executing right
  692  to use a qualified contractor of the applicant’s choosing,
  693  within the scope of the contractor’s professional licensure and
  694  as authorized under this section, to perform technical review
  695  and certification necessary to support the issuance of up to 75
  696  percent of the building permits for the residential subdivision
  697  or planned community, including one or more phases thereof,
  698  before the final plat is recorded, provided the qualified
  699  contractor does not have a conflict of interest. For the
  700  purposes of this paragraph, the term “conflict of interest” has
  701  the same meaning as in s. 112.312.
  702         b.The governing body, local building official, and any
  703  local government staff may not condition, delay, limit,
  704  restrict, obstruct, or deny the applicant’s use of a qualified
  705  contractor under this paragraph. This paragraph does not
  706  prohibit a local government from applying neutral, generally
  707  applicable requirements relating to procurement, contracting,
  708  insurance, indemnification, conflict-of-interest review,
  709  credential verification, recordkeeping, or public safety,
  710  provided such requirements do not materially impair or frustrate
  711  the applicant’s ability to use a qualified contractor as
  712  authorized by this paragraph. Any local requirement that
  713  directly conflicts with this paragraph is preempted to the
  714  extent of the conflict.
  715         c.The qualified contractor may perform all technical
  716  review services within the scope of his or her licensure and
  717  qualifications which are necessary to obtain such building
  718  permits as specifically authorized under this section, including
  719  preparing, reviewing, and submitting permit applications and
  720  supporting plans, specifications, and documents, and providing
  721  signed and sealed documents when required by law. The local
  722  building official must accept such submissions when prepared and
  723  sealed by the qualified contractor as meeting any local
  724  requirement that the submission be prepared or reviewed by local
  725  government staff, and must review and issue the permits in
  726  accordance with the Florida Building Code and applicable state
  727  law. This paragraph does not limit the authority of the local
  728  building official to review such submission by a qualified
  729  contractor for compliance with the Florida Building Code and
  730  applicable state law, to identify deficiencies, or to approve or
  731  deny the permit in accordance with the law.
  732         d.The governing body and the local building official may
  733  not unreasonably require the applicant or the qualified
  734  contractor to use a local government registry, rotation, or
  735  shortlist, or any other selection or vetting process, which has
  736  the effect of denying or materially delaying the applicant’s use
  737  of a qualified contractor under this section..
  738         e.The unconditional right provided by this paragraph
  739  becomes effective immediately upon the governing body’s failure
  740  to meet the applicable deadlines in paragraph (a) or paragraph
  741  (c), continues in effect unless and until the governing body has
  742  adopted or updated a program fully compliant with this section,
  743  and may not be limited, impaired, or applied retroactively to
  744  reduce the number or percentage of building permits the
  745  applicant may obtain or is eligible to obtain under this
  746  paragraph.
  747         2.This paragraph may not be construed to limit or impair
  748  the authority of the local building official to enforce the
  749  Florida Building Code, the Florida Fire Prevention Code, or
  750  other applicable state laws and local laws of general
  751  application in reviewing and issuing building permits; however,
  752  the governing body and the local building official may not
  753  impose any additional local procedures, prerequisites, or
  754  substantive standards on the applicant or the qualified
  755  contractor which have the effect of conditioning, delaying,
  756  restricting, or denying the use of a qualified contractor as
  757  authorized by this paragraph.
  758         (3) A governing body shall create:
  759         (a) A two-step application process for the adoption of a
  760  preliminary plat, and for stabilized access roads that can
  761  support emergency vehicles, inclusive of any plans, in order to
  762  expedite the issuance of building permits under this section.
  763  The application must allow an applicant to identify the
  764  percentage of planned homes or the number of building permits
  765  that the governing body must issue for the residential
  766  subdivision, or planned community, or one or more phases of a
  767  multiphased planned community or subdivision.
  768         (4)(a) An applicant may use a private provider or qualified
  769  contractor in the same manner as provided in pursuant to s.
  770  553.791 to expedite the application process for building permits
  771  after a preliminary plat is approved under this section.
  772         (b) A governing body shall, upon the written request of the
  773  applicant, use the qualified contractor registry established in
  774  s. 163.3169 establish a registry of at least three qualified
  775  contractors whom the governing body may use to supplement staff
  776  resources in ways determined by the governing body for
  777  processing and expediting the review of an application for a
  778  preliminary plat or any plans related to such application. A
  779  qualified contractor on the registry who is hired pursuant to
  780  this section to review an application, or any part thereof, for
  781  a preliminary plat, or any part thereof, may not have a conflict
  782  of interest with the applicant. For purposes of this paragraph,
  783  the term “conflict of interest” has the same meaning as in s.
  784  112.312.
  785         (6) The governing body must issue the number or percentage
  786  of building permits requested by an applicant in accordance with
  787  the Florida Building Code and this section, provided the
  788  residential buildings or structures are unoccupied and all of
  789  the following conditions are met:
  790         (b) The applicant provides proof to the governing body that
  791  the applicant has provided a copy of the approved preliminary
  792  plat, along with the approved plans, to the relevant electric,
  793  gas, water, and wastewater utilities. For purposes of this
  794  paragraph, the term “approved plans” means plans approved for
  795  design and permit review and does not include, and may not be
  796  construed to require or imply, any certification, attestation,
  797  or confirmation of the completion of construction of any
  798  subdivision or planned community infrastructure, or improvements
  799  depicted in, referenced by, or required under such plans, except
  800  for the construction of the minimum access and roadway
  801  improvements required by the Florida Fire Prevention Code for
  802  fire department access and operations, such as a stabilized
  803  roadway for emergency access. No other subdivision or planned
  804  community infrastructure or improvements may be required to be
  805  constructed as a condition of building permit issuance or
  806  approval authorized under this section.
  807         1.A local government may not condition, delay, withhold,
  808  or deny the issuance of any building permit authorized under
  809  this section on:
  810         a.The actual completion, substantial completion, or
  811  physical installation of any subdivision or planned community
  812  infrastructure, or improvements identified in the approved
  813  preliminary plat or approved plans;
  814         b.The submission, acceptance, or approval of any
  815  certification of completion or similar documentation, including,
  816  but not limited to, certificates of completion or substantial
  817  completion, engineer’s or architect’s certifications of
  818  completion, as-built or record drawings, pressure or compaction
  819  test results, utility acceptance letters, service availability
  820  letters, or similar confirmations of finished construction or
  821  readiness for service; or
  822         c.Compliance with an environmental condition which is not
  823  required by its land development regulations, a local government
  824  comprehensive plan, a regulatory covenant or similar recorded
  825  instrument, a decision or order by a local zoning board or other
  826  quasi-judicial board, or by state law or federal law to obtain a
  827  building permit.
  828         2.This prohibition applies notwithstanding any ordinance,
  829  resolution, policy, practice, permit condition, concurrency or
  830  proportionate-share requirement, interlocal agreement, utility
  831  policy or standard, or other local requirement to the contrary.
  832         3.This paragraph may not be construed to prohibit a local
  833  government from requiring documentation strictly necessary to
  834  demonstrate compliance with the Florida Fire Prevention Code as
  835  a condition of issuing building permits; however, such
  836  documentation may not require the physical completion of the
  837  subdivision or planned community infrastructure, or improvements
  838  beyond what is expressly required to satisfy the Florida Fire
  839  Prevention Code.
  840  
  841  This paragraph may not be construed to relieve an applicant from
  842  completing or installing any infrastructure or improvements as a
  843  condition of issuance of a certificate of occupancy.
  844         (c) The applicant holds a valid performance bond for up to
  845  130 percent of the necessary improvements, as defined in s.
  846  177.031(9), that have not been completed upon submission of the
  847  application under this section. For purposes of a master planned
  848  community as defined in s. 163.3202(5)(b), a valid performance
  849  bond is required on a phase-by-phase basis. For purposes of this
  850  section, a local government may waive the bond requirement in
  851  this paragraph through its program or on a case-by-case basis
  852  upon request of the applicant.
  853         (8) For purposes of this section, an applicant has a vested
  854  right in a preliminary plat that has been approved by a
  855  governing body for the earlier of at least 5 years or if all of
  856  the following conditions are met:
  857         (a) The applicant relies in good faith on the approved
  858  preliminary plat or any amendments thereto.
  859         (b) The applicant incurs obligations and expenses,
  860  commences construction of the residential subdivision or planned
  861  community, and is continuing in good faith with the development
  862  of the property.
  863         Section 6. This act shall take effect July 1, 2026.
  864  
  865  ================= T I T L E  A M E N D M E N T ================
  866  And the title is amended as follows:
  867         Delete everything before the enacting clause
  868  and insert:
  869                        A bill to be entitled                      
  870         An act relating to qualified contractors; amending ss.
  871         125.022 and 166.033, F.S.; requiring each county and
  872         municipality, respectively, of a specified size to
  873         create and implement a program for the purpose of
  874         making development preapplication consultation
  875         services available at an applicant’s request;
  876         providing that specified provisions may not be
  877         construed to affect or require the modification of
  878         certain county or municipality programs that make
  879         available the same or substantially similar
  880         development preapplication consulting services if such
  881         county or municipality’s program existed before a
  882         specified date; limiting such preapplication
  883         consultation services to applications for certain
  884         permits; authorizing a county or municipality to use a
  885         qualified contractor or qualified contractor firm to
  886         fulfill specified preapplication services
  887         requirements; specifying minimum requirements for a
  888         development preapplication consultation services
  889         program; requiring a county or municipality to take
  890         certain actions if an applicant chooses to use the
  891         development preapplication consultation services
  892         program; requiring a county or municipality to
  893         approve, approve with conditions, or deny an
  894         applicant’s completed application within a specified
  895         timeframe; requiring that an application be deemed
  896         approved by operation of law without conditions and
  897         proceed in a specified manner if a county or
  898         municipality fails to make a certain determination
  899         within a specified timeframe; providing construction;
  900         specifying that certain requirements apply if an
  901         applicant for a development permit or development
  902         order is not eligible for, does not request, or elects
  903         not to use the county’s or municipality’s
  904         preapplication consulting services program; creating
  905         s. 163.3169, F.S.; defining terms; requiring a local
  906         government to establish a registry of a specified
  907         number of qualified contractors or qualified
  908         contractor firms to conduct certain preapplication
  909         services; prohibiting a qualified contractor or
  910         qualified contractor firm from having a conflict of
  911         interest; authorizing an applicant to use a qualified
  912         contractor that is not on the registry if a conflict
  913         of interest exists; authorizing a local government to
  914         enter into a certain agreement with another local
  915         government under certain circumstances; prohibiting a
  916         local government from adding its own employees to the
  917         registry; authorizing an applicant to retain a
  918         qualified contractor or qualified contractor firm of
  919         his or her choosing for preapplication consultation
  920         services under certain circumstances; prohibiting a
  921         local government from conditioning, denying, or
  922         delaying an applicant’s selection or use of a
  923         qualified contractor or qualified contractor firm;
  924         specifying that the applicant is responsible for all
  925         fees and costs associated with using a qualified
  926         contractor of his or her choice; requiring a local
  927         government to make certain resources available if an
  928         applicant uses a qualified contractor or qualified
  929         contractor firm of his or her choosing to perform
  930         preapplication consultation services; providing an
  931         exception; providing construction; amending s.
  932         177.071, F.S.; authorizing a governing body to use a
  933         specified registry to supplement local government
  934         staff resources; prohibiting a local government from
  935         creating, establishing, or applying any additional
  936         local procedure or condition for the administrative
  937         approval of a plat or replat which is inconsistent
  938         with specified provisions; authorizing the
  939         administrative authority to receive and act upon
  940         certain financial assurances; providing requirements
  941         for a local government’s acceptance of certain
  942         financial assurances; amending s. 177.073, F.S.;
  943         revising the definition of the term “applicant”;
  944         requiring the governing body of certain local
  945         governments and counties to include certain
  946         developments in a program that expedites the process
  947         for issuing building permits for planned unit
  948         developments or phases of a community or subdivision;
  949         specifying automatic actions in the event the local
  950         government fails to adopt, update, or modify a certain
  951         program by a specified date; defining the term
  952         “conflict of interest”; providing construction;
  953         requiring a governing body to create a two-step
  954         application process for stabilized access roads that
  955         can support emergency vehicles; revising requirements
  956         for such application process; authorizing an applicant
  957         to use a qualified contractor for land use approvals
  958         under certain circumstances; authorizing a governing
  959         body to use the qualified contractor registry
  960         established pursuant to this act to supplement staff
  961         resources; deleting provisions prohibiting the use of
  962         a qualified contractor with a conflict of interest;
  963         defining the term “approved plans”; providing
  964         construction; prohibiting a local government from
  965         conditioning, delaying, withholding, or denying the
  966         issuance of certain permits under certain
  967         circumstances; providing applicability; providing
  968         construction; authorizing a local government to waive
  969         a certain bond requirement under certain
  970         circumstances; revising the circumstances under which
  971         an applicant has a vested right in a preliminary plat;
  972         providing an effective date.