Sewer Rehabilitation in Area 1, and expansion of Lift Station SCADA system
 
Requester: Jim Hanson, City Manager Organization: City of Atlantic Beach
 
Project Title: Sewer Rehabilitation in Area 1, and expansion of Lift Station SCADA system Date Submitted 12/23/2003 2:30:44 PM
 
Sponsors: Wise
 
Statewide Interest:
Need for sewer improvements which will help to protect the environment and the public health.
 
Recipient: City of Atlantic Beach   Contact: Donna Kaluzniak, Utility Director  
  800 Seminole Road   Contact Phone: (904) 247-5834  
  Atlantic Beach 32233   Contact email:  
 
Counties: Duval
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
Sewer system rehabilitation in priority area of the City as based on the City's Sewer Master Plan 2000. Area 1 is bordered by Dutton Island Road West, Levy Road, west of Main Street and Mayport Road. Areas were identified in the Sewer Master Plan as having the highest amount of inflow/infiltration into the sewer system, which has resulted in past sanitary sewer overflows during heavy rainfall periods. The rehabilitation methods may include a combination of point repairs, cured in place piping, pipe replacements, and manhole repair or replacement. Expansion of the lift station SCADA system will include lift stations on Stewart Street, Seminole Road, Camelia Street, Monmouth Court, Aspen Ridge, Montreal, West End and Featherwood. The SCADA system will include alarms and automatic dial-out to help prevent sanitary sewer overflows caused by lift station problems.
 
Is this a water project as described in Chapter 2002-291, Laws of Florida? Yes
Has the project been submitted to the Department of Environmental Protection? Yes
DEP Identfying Number: WW20032012
 
Measurable Outcome Anticipated:
Reduce response time for lift station malfunctions, reduce number of sanitary sewer overflows.
 
Amount requested from the State for this project this year: $100,000
 
Total cost of the project: $200,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local
  Cash Amount $100,000  
 
Was this project previously funded by the state?   No
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   No
 
Was this project included in the Governor's Recommended Budget? No
 
Is there a documented need for this project? Yes
  Documentation: Sewer Master Plan, City of Atlantic Beach
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: City of Atlantic Beach City Commisssion, Approved Sewer Master Plan on November 13,2000