Community Budget Issue Requests - Tracking Id #1472
Cascade Park Remediation
 
Requester: City of Tallahassee Organization: City of Tallahassee
 
Project Title: Cascade Park Remediation Date Submitted 1/12/2005 2:53:10 PM
 
Sponsors: Argenziano, Lawson
 
Statewide Interest:
This project represents a significant economic development opportunity that will stimulate needed development in this area of the community.
 
Recipient: City of Tallahassee   Contact: Dinah Hart  
  300 South Adams Street   Contact Phone: (850) 891-8181  
  Tallahassee 32301   Contact email: hartd@talgov.com
 
Counties: Leon
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
Remediation of contamination at the Cascade Park Manufactured Gas Plant and Cascade Landfill. This property is the site of a former coal gasification plant and has been the subject of a federal Administrative Order on Consent(AOC) through the US Environmental Protection Agency(EPA). The property is located adjacent to the Capitol complex, within Southern Strategies Boudaries. Not only is it currently unusable for citizens and visitors to this community, but it also is a significant impediment to economic development in the area. Enhancements to the Cascades Park area are planned, funded by local option
 
Is this a project related to 2004 hurricane damage? No
 
Measurable Outcome Anticipated:
The return of the envrionmentally impaired sites within the Cascades Park property to productive community development uses, in accordance with EPA and state agreements.
 
Amount requested from the State for this project this year: $3,000,000
 
Total cost of the project: $3,800,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local
  Cash Amount $1,000,000  
 
Was this project previously funded by the state?   Yes
  Fiscal Year: 2004-2005 Amount: $1,200,000
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   No
 
Was this project included in the Governor's Recommended Budget? No
 
Is there a documented need for this project? Yes
  Documentation: EPA Administrative Order of Consent
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: City of Tallahassee
  Hearing Meeting Date: 10/27/2004
 
Is this a water project as described in Section 403.885, Laws of Florida?   No