Widening of Capital Circle Northwest from I-10 to US 90
 
Requester: City of Tallahassee Organization: City of Tallahassee
 
Project Title: Widening of Capital Circle Northwest from I-10 to US 90 Date Submitted 1/12/2005 3:30:34 PM
 
Sponsors: Argenziano, Lawson
 
Statewide Interest:
The widening of this section of Capital Circle provides a much needed intermodal connector between the Tallahassee Regional Airpot and the major limited access highway in the southern United States, I-10. Currently, connections are made to I-10 using congested urban arterials, which generally impede freight movements, given the amount of local traffic dependent on Captial Circle NW/SW for local area traffic movement.
 
Recipient: City of Tallahassee   Contact: Dinah Hart  
  300 South Adams Street   Contact Phone: (850) 891-8181  
  Tallahassee 32301   Contact email: hartd@talgov.com
 
Counties: Leon
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
Capital Circle is a major arterial roadway circling the Tallahassee urban area. It links a major expressway(I-10) with US 27 and US 90. Other segments of Capital Circle have been widened with a significant portion of the improvements being either directly funded or advance-funded by the City of Tallahassee or Leon County. The segment of Capital Circle being requested is I-10 to US90, which is one of the remaining Captial Circle sections to be imporved, and is the most critical section of the intermodal link from the Tallahassee Regional Airport to I-10. This two-lane route carries freight traffic from industrial land uses and the airport, the primary intermodal facility between jacksonville and Pensacola. This application is consistent with local planning initiatives, including the Captial Regional Transportation Planning Agency's 2020 Transportation Plan, as the I-10 to US90 section is the number one transportation priority for the current year.
 
Is this a project related to 2004 hurricane damage? No
 
Measurable Outcome Anticipated:
The Tallahassee and Leon County Commissions, through their "Southern Strategy" initiative are attempting to spur economic growth in the souther areas of the City and County with a combination of roadway improvements, sector-planning efforts, growth management and economic incentives. Targeted, is the southwestern quadrant, an area serviced by Capital Circle Northwest/Southwest. The Tallahassee Airport is in the midst of a major passenger growth, which will generate new jobs, enhancing its role as an intermodal facility for the region, and generate new demands on the roadway infrastructure. Capital Circle Northwest/Southwest is also a critical transportation link needed to facilitate the efficient emergency evacuations of residents from low-lying or vulnerable coastal areas.
 
Amount requested from the State for this project this year: $26,500,000
 
Total cost of the project: $54,200,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? None
  Cash Amount $  
 
Was this project previously funded by the state?   Yes
  Fiscal Year: 2001-2002 Amount: $550,000
 
Is future-year funding likely to be requested?   No
 
Was this project included in an Agency's Budget Request?   No
 
Was this project included in the Governor's Recommended Budget? No
 
Is there a documented need for this project? Yes
  Documentation: This segment of the roadway is the number one priority in Tallahassee Leon County MPO fy2005-2009
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: Tallahassee Leon County Cap Regional Trans Planning Agency
  Hearing Meeting Date: 09/15/2004
 
Is this a water project as described in Section 403.885, Laws of Florida?   No