Community Budget Issue Requests - Tracking Id #1747 |
Weatherization |
|
Requester: |
Lelia Allen |
Organization: |
City of Orlando |
|
Project Title: |
Weatherization |
Date Submitted |
2/24/2005 3:24:14 PM |
|
Sponsors: |
Siplin |
|
Statewide Interest: |
This project will provide weatherization and other energy reduction savings measures for homes of very low and low-income households in the Parramore neighborhood of Orlando. The neighborhood consists of 325 owner- occupied homes, of which elderly or disabled persons occupy the majority, and that are desperate need of repairs for their homes. A special task force has completed a study of the needs of the housing stock and has concluded that rehabilitation and weatherization is needed. |
|
Recipient: |
City of Orlando |
|
Contact: |
Lelia Allen, Director Housing Department |
|
|
400 S. Orange Avenue |
|
Contact Phone: |
(407) 246-2292 |
|
|
Orlando 32801-4990 |
|
Contact email: |
lelia.allen@cityoforlando.net |
|
Counties: |
Orange |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
This project provides weatherization services and supplemental repairs to the dwellings of very low and low-income households. Repairs may include, but not be limited to plumbing, electrical, painting, installation of windows, doors, etc. This project will be implemented utilizing the succesful model developed for the city of Winter Garden in 2002, which allowed for more than the basic |
|
Is this a project related to 2004 hurricane damage? |
No |
|
Measurable Outcome Anticipated: |
Repairs and improvements to approximately 90 homes saving approximately $90,000 per year in energy costs or an average of $1,285 per residence. |
|
Amount requested from the State for this project this year: |
$900,000 |
|
Total cost of the project: |
$900,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Federal |
|
Cash Amount |
$750,000 |
|
In-kind Amount |
$50,000 |
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
No |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
Yes |
|
Documentation: |
Mayor's Parramore Task Force Report and City of Orlando Housing Condition Survey |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
Yes |
|
Hearing Body: |
Parramore Task Force |
|
Hearing Meeting Date: |
02/23/2004 |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
No |