Community Budget Issue Requests - Tracking Id #207 |
Stormwater System Major Restoration |
|
Requester: |
David Brown |
Organization: |
City of Coral Gables |
|
Project Title: |
Stormwater System Major Restoration |
Date Submitted |
1/14/2005 2:00:24 PM |
|
Sponsors: |
Margolis |
|
Statewide Interest: |
To provide flood protection to low-lying areas in the City of Coral Gables. |
|
Recipient: |
City of Coral Gables |
|
Contact: |
Maria Jimenez, Assistant City Manager |
|
|
405 Biltmore Way |
|
Contact Phone: |
(305) 460-5204 |
|
|
Coral Gables 33134 |
|
Contact email: |
mjimenez@coralgables.com |
|
Counties: |
Dade |
|
Gov't Entity: |
Yes |
Private Organization (Profit/Not for Profit): |
|
|
Project Description: |
Rehabilitation of approximately 3,000 linear feet of stormwater pipe ranging from 15" to 36" in diameter by cleaning and removing build up of bi-valve organisms and relining same. The work will require equipment that is not readily available. Conditions will be difficult as piping may be totally submerged. |
|
Is this a project related to 2004 hurricane damage? |
No |
|
Measurable Outcome Anticipated: |
Based on initial inspections, average pipe cross section area is reduced by 50% or more. Therefore, flow rates in these pipes will be restored to 100% capacity. |
|
Amount requested from the State for this project this year: |
$375,000 |
|
Total cost of the project: |
$500,000 |
|
Request has been made to fund: |
Construction |
|
What type of match exists for this project? |
Local |
|
Cash Amount |
$75,000 |
|
In-kind Amount |
$50,000 |
|
Was this project previously funded by the state? |
|
No |
|
Is future-year funding likely to be requested? |
|
Yes |
|
Amount: |
$375,000 |
To Fund: |
Operations, Construction, To complete this project |
|
Was this project included in an Agency's Budget Request? |
|
No |
|
Was this project included in the Governor's Recommended Budget? |
No |
|
Is there a documented need for this project? |
No |
|
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)? |
|
No |
|
Is this a water project as described in Section 403.885, Laws of Florida? |
|
Yes |
Has the project been submitted to the Department of Environmental Protection? |
No |
Is this project eligible under section 403.885(5) F.S.? |
Yes |
|
Is your project addressed in a state, regional or local plan (such as a SWIM plan, Comprehensive Plan, local master plan, etc.)? |
No |
|
If you are requesting funding for a stormwater or surface water restoration project: |
|
Which Water Management District has the jurisdiction of your project? |
|
South Florida Water Management District |
Have you provided at least 50% match? |
No |
|
Will this project reduce pollutant loadings to a water management district designated 'priority' surface water body? |
No |
|
If you are requesting funding for a wastewater project: |
|
Does your project qualify for funding from DEP's 'Small Community Wastewater Treatment Grant Program' under section 403.1838 F.S.? |
No |
|
Other wastewater projects: |
|
Have you received previous legislative funding for this project? |
No |
|
Is the project under construction? |
No |
|
Have you provided at least a 25% local match? |
No |