CBIRS Request 383
 
Community Budget Issue Requests - Tracking Id #383
Middle St. John's River Basin Initiative
 
Requester: Board of County Commissioners Organization: Seminole County Government
 
Project Title: Middle St. John's River Basin Initiative Date Submitted 1/14/2004 12:42:02 PM
 
Sponsors: Cowin
 
Statewide Interest:
Surface water restoration
 
Recipient: St. Johns Water Management District   Contact: Mark Flomerfelt  
  P.O. Box 1429   Contact Phone: (407) 665-5610  
  Palatka 32178   Contact email: mflomerfelt@co.seminole.fl.us
 
Counties: Seminole
 
Gov't Entity: Yes Private Organization (Profit/Not for Profit):  
 
Project Description:
The Middle St. Johns River Basin Initiative is an ongoing project to restore and enhance the middle St. Johns River and its tributaries. This basin is an area where population and water use are expected to grow. Funding through this initiative will help to restore and enhance this portion of the river and its lakes and tributaries. Examples of subprojects that could be funded through this request follow. This list is in alphabetical order and is not a complete listing: Econolockhatchee River Watershed, Lake Jesup Restoration - Tributary Stormwater Parks Assessment and Implementation, Lake Jesup Stormwater Retrofits, Lake Monroe Watershed Plan Implementation, Little Econlockhatchee River Watershed Improvements, Little Wekiva River Watershed Management Implementation
 
Is this a water project as described in Chapter 2002-291, Laws of Florida? Yes
Has the project been submitted to the Department of Environmental Protection? Yes
DEP Identfying Number: PENDING
 
Measurable Outcome Anticipated:
the Middle St. Johns River Basin Initiative will protect the environment through support of partnership projects between local governments of the middle basin and the District to implement projects identified within watershed management plans by the partners. The subprojects are identified to reduce pollutants being discharged to surface waters as untreated stormwater runoff and to target areas that were developed prior to current stormwater treatment rules. The subprojects have undergone analyses and prioritization to provide the greatest pollutant removal and benefit to the waters of the state that is possible, Wekiva, Econlockhatchee, and middle St. Johns Rivers.
 
Amount requested from the State for this project this year: $4,000,000
 
Total cost of the project: $100,000,000
 
Request has been made to fund: Construction
 
What type of match exists for this project? Local, Federal
  Cash Amount $80,000,000  
 
Was this project previously funded by the state?   Yes
  Fiscal Year: 2002-2003 Amount: $3,000,000
 
Is future-year funding likely to be requested?   Yes
  Amount: $4,000,000 To Fund: Construction
 
Was this project included in an Agency's Budget Request?   Yes
  Agency Environmental Protection, Department Of
 
Was this project included in the Governor's Recommended Budget? Unknown
 
Is there a documented need for this project? Yes
  Documentation: Middle St. Johns River Basin Initiative Report dated 12/17/2002 and all supporting documents.
 
Was this project request heard before a publicly noticed meeting of a body of elected officials (municipal, county, or state)?   Yes
  Hearing Body: Seminole Legislative Delegation
  Hearing Meeting Date: 12/17/2003